13490-13492 W DYER ST 91342

Certificate Information: 13490-13492 W DYER ST 91342

Application / Permit
22014-20000-00847
Plan Check / Job No.
B22VN02887
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 16' X 29'-6" ADDITION AND REMODEL TO (E) SFD FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER WFPP.
Permit Issued
Issued on 8/18/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2022 APPLICANT
Assigned to Plan Check Engineer 2/28/2022 RAPHAEL ROSAS
Corrections Issued 2/28/2022 RAPHAEL ROSAS
Building Plans Picked Up 3/17/2022 APPLICANT
Applicant returned to address corrections 8/9/2022 DANIEL ABRAMYAN
Plan Check Approved 8/18/2022 OMAR GARNICA
Issued 8/18/2022 APPLICANT
CofO in Progress 10/4/2024 KEVIN BERBERYAN
Permit Finaled 10/23/2024 DANIEL ORRANTE
CofO Issued 10/23/2024 DANIEL ORRANTE
Permit Finaled 10/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/19/2022 CARLOS AGUILERA
Construction near power lines Cleared 5/10/2022 RIDWAN HARDY
Low Impact Development Cleared 6/20/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 6/21/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/11/2022 CARLOS AGUILERA
Sewer availability Cleared 8/11/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/19/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/23/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/6/2023 Partial Approval JOHN COLEMAN
PLUMBING-Rough 3/6/2023 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 4/14/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/14/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 4/24/2023 Approved ARAM AVEDISIAN
Green Building Rough 4/24/2023 Approved ARAM AVEDISIAN
HVAC-Rough 4/24/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 4/24/2023 Partial Approval ARAM AVEDISIAN
Insulation 4/27/2023 Approved ARAM AVEDISIAN
Shower Pan 4/27/2023 Approved ARAM AVEDISIAN
Drywall Nailing 5/2/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/2/2023 Partial Approval ARAM AVEDISIAN
Final 9/29/2023 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/29/2023 Conditional Approval KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/29/2023 Approved KEVIN BERBERYAN
Final 9/18/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/18/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 10/4/2024 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 10/4/2024 Approved KEVIN BERBERYAN