7322-7324 N PONCE AVE 91307

Certificate Information: 7322-7324 N PONCE AVE 91307

Application / Permit
22014-20000-00846
Plan Check / Job No.
B22VN02886
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO JADU PER STATE LAW
Permit Issued
Issued on 4/27/2022
Issuing Office
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2022 APPLICANT
Assigned to Plan Check Engineer 2/28/2022 CARLOS MONTES
Corrections Issued 3/1/2022 CARLOS MONTES
Plan Check Approved 4/20/2022 CARLOS MONTES
Issued 4/27/2022 APPLICANT
CofO in Progress 11/1/2022 CHRIS CHRISTENSEN
CofO Issued 2/14/2023 JOHN JANSON
Permit Finaled 2/14/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/4/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/4/2022 CARLOS AGUILERA
Sewer availability Cleared 3/4/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/25/2022 Partial Approval CHRIS CHRISTENSEN
Sewer 5/25/2022 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/3/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/29/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/29/2022 Approved CHRIS CHRISTENSEN
Wood Frame 6/29/2022 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/7/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 7/7/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 7/13/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 7/13/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/13/2022 Partial Approval CHRIS CHRISTENSEN
Shower Pan 7/13/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/15/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 7/15/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 7/25/2022 Approved KRISTEN CAUSEY
ELECTRICAL-Final 9/15/2022 Approved CHRIS CHRISTENSEN
Final 9/15/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 9/15/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 9/15/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 9/15/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 9/15/2022 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 9/16/2022 Conditional Approval CHRIS CHRISTENSEN
Final 10/11/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 10/31/2022 OK to Issue CofO CHRIS CHRISTENSEN