6633 N COLBATH AVE 91405
Certificate Information: 6633 N COLBATH AVE 91405
- Application / Permit
- 22014-20000-00838
- Plan Check / Job No.
- B22VN02856
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL; REMOVE ENTIRE DWELLING (33 LINEAR FEET OF WALL TO REMAIN ON NORTH SIDE OF BUILDING) AND 2ND FLOOR ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH NEW ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Current Status
- CofO Issued on 12/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | SELLA BENYAMIN |
| Corrections Issued | 3/15/2022 | SELLA BENYAMIN |
| Quality Review Completed | 3/17/2022 | STEVEN KIM |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Plan Check Approved | 5/19/2022 | SELLA BENYAMIN |
| Issued | 5/31/2022 | APPLICANT |
| CofO in Progress | 11/22/2024 | RYAN SALAZAR |
| Permit Finaled | 12/10/2024 | RUBEN SALAS |
| CofO Issued | 12/10/2024 | RUBEN SALAS |
| Permit Finaled | 12/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/18/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 4/21/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 4/21/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/25/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 8/29/2022 | Conditional Approval | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 8/30/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 8/30/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 9/26/2022 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 9/26/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 10/3/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 10/18/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/25/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 10/25/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 10/25/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Partial Approval | RICHARD DOCKUS |
| Deputy Wood Construction | 11/1/2022 | Conditional Approval | MICHAEL SMITH |
| Deputy Steel/Welding | 11/7/2022 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 11/9/2022 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 11/9/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Structural Steel Frame | 11/9/2022 | Partial Inspection | RICHARD DOCKUS |
| Deputy Wood Construction | 11/10/2022 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 1/24/2023 | Approved | RYAN SALAZAR |
| Deck | 1/24/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/24/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 1/24/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/21/2023 | Partial Approval | RYAN SALAZAR |
| Insulation | 5/10/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 5/10/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/13/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/13/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 11/30/2023 | Approved | RYAN SALAZAR |
| Pre-Inspection | 3/20/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Pre-Inspection | 4/3/2024 | Partial Inspection | RYAN SALAZAR |
| Service/Power Release | 4/15/2024 | Approved | RYAN SALAZAR |
| Pre-Inspection | 6/13/2024 | Partial Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/16/2024 | Approved | RYAN SALAZAR |
| Final | 9/16/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 9/16/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 9/16/2024 | Approved | RYAN SALAZAR |
| Pre-Inspection | 9/16/2024 | Partial Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/16/2024 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 9/16/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 11/21/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 11/21/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 11/21/2024 | Approved | RYAN SALAZAR |