4518 S 4TH AVE 90043
Certificate Information: 4518 S 4TH AVE 90043
- Application / Permit
- 22014-20000-00804
- Plan Check / Job No.
- B22VN02724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 18' X 13' ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT (418 SQ FT) PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 2/26/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/30/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/31/2022 | APPLICANT |
| Issued | 5/10/2022 | APPLICANT |
| Refund in Progress | 7/29/2022 | TERENCE SHIA |
| Refund Withdrawn | 8/4/2022 | EMILY HU |
| Issued | 8/4/2022 | EMILY HU |
| CofO in Progress | 1/9/2024 | ANTHONY EGSON |
| Permit Finaled | 1/30/2024 | DEROLD HAUFF |
| CofO Issued | 1/30/2024 | DEROLD HAUFF |
| Permit Finaled | 1/30/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 3/7/2022 | CELINA MORENO |
| Sewer availability | Cleared | 3/7/2022 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Contractor | Pro Star Builders Inc; Lic. No.: 1053661-B | 17412 VENTURA BLVD SUITE 151 ENCINO, CA 91316 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/28/2022 | Approved | ANTHONY EGSON |
| Pre-Inspection | 6/28/2022 | Partial Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/5/2022 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 7/20/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/28/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 7/28/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/28/2022 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/1/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 8/1/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/1/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 8/1/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/10/2022 | Approved | ANTHONY EGSON |
| Insulation | 8/15/2022 | Partial Approval | ANTHONY EGSON |
| Drywall Nailing | 8/17/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 9/26/2022 | No Access for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/18/2022 | No Access for Inspection | ANTHONY EGSON |
| Shower Pan | 10/18/2022 | No Access for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/19/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 10/19/2022 | Corrections Issued | ANTHONY EGSON |
| Shower Pan | 11/3/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 11/14/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/22/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/22/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/22/2022 | Approved | ANTHONY EGSON |
| Sewer | 12/22/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Not Ready | ANTHONY EGSON |
| ELECTRICAL-Final | 1/3/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 1/3/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/3/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 1/3/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 1/3/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 2/8/2023 | Corrections Issued | SCOTT FINNILA |
| Gas Test | 2/8/2023 | Approved | SCOTT FINNILA |
| Green Building Final | 2/8/2023 | Approved | SCOTT FINNILA |
| Pre-Inspection | 2/8/2023 | Partial Inspection | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 2/8/2023 | Approved | SCOTT FINNILA |
| Final | 2/24/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 3/15/2023 | No Access for Inspection | ANTHONY EGSON |
| Final | 3/22/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 4/14/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 4/27/2023 | Approved | ANTHONY EGSON |
| Final | 4/27/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/27/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 4/27/2023 | Approved | ANTHONY EGSON |
| Final | 1/8/2024 | OK to Issue CofO | ANTHONY EGSON |