15434 W VISTA HAVEN PL 91403
Certificate Information: 15434 W VISTA HAVEN PL 91403
- Application / Permit
- 22014-20000-00794
- Plan Check / Job No.
- B22VN02698
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (39'-6"x 18'-10") IRR SHAPE AT REAR, EXPAND (15'-7"x 2'-5") AT FRONT BEDROOM & ADD/ CONNECT ( 18'-3"x 17'-0") MAIDS ROOM @ (E) DET. GARAGE AND MAJOR REMODEL TO (E) ONE STORY SINGLE FAMILY DWELLING, WITH NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Current Status
- CofO Issued on 7/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | TROY DEGUZMAN |
| Corrections Issued | 3/8/2022 | TROY DEGUZMAN |
| Quality Review Completed | 3/10/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Applicant returned to address corrections | 4/26/2022 | TROY DEGUZMAN |
| Plan Check Approved | 5/3/2022 | TROY DEGUZMAN |
| Issued | 5/3/2022 | APPLICANT |
| CofO in Progress | 7/5/2023 | THOMAS FINNILA |
| Permit Finaled | 7/28/2023 | RUBEN SALAS |
| CofO Issued | 7/28/2023 | RUBEN SALAS |
| Permit Finaled | 7/28/2023 | RUBEN SALAS |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 3/6/2022 | TIMOTHY POWELL |
| Grading Pre-Inspection | Cleared | 3/6/2022 | TIMOTHY POWELL |
| Address approval | Cleared | 3/7/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 3/7/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 3/7/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 3/7/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 3/7/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/8/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 3/17/2022 | CARLOS AGUILERA |
| Specific Plan | Cleared | 4/5/2022 | OLGA AYALA |
| ZI | Cleared | 4/5/2022 | OLGA AYALA |
| Low Impact Development | Cleared | 4/14/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 4/19/2022 | ABDULLAH SADOZAI |
| Hydrant and Access approval | Cleared | 4/22/2022 | KURT CORRAL |
| Green Code | Cleared | 4/26/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Classic Remodeling; Lic. No.: 980373-B | 12830 BURBANK BLVD #317 NORTH HOLLYWOOD, CA 91607 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/24/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 5/26/2022 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 5/31/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/6/2022 | Corrections Issued | MATT KELLERMAN |
| Footing/Foundation/Slab | 6/10/2022 | No Access for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/16/2022 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 8/30/2022 | Approved | JACK KARGODORIAN |
| Deputy Steel/Welding | 9/14/2022 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 9/22/2022 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/14/2022 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/20/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 10/20/2022 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/26/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 10/26/2022 | Approved | THOMAS FINNILA |
| Insulation | 10/26/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/26/2022 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 10/26/2022 | Approved | THOMAS FINNILA |
| Shower Pan | 10/26/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/26/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 11/1/2022 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/1/2022 | Approved | THOMAS FINNILA |
| Shower Pan | 11/1/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 3/17/2023 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 3/17/2023 | Approved | THOMAS FINNILA |
| Drywall Nailing | 6/21/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 6/21/2023 | Approved | THOMAS FINNILA |
| HVAC-Final | 6/21/2023 | Approved | THOMAS FINNILA |
| MERV13>=Final | 6/21/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 6/21/2023 | Approved | THOMAS FINNILA |
| Final | 7/3/2023 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 7/3/2023 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Approved | THOMAS FINNILA |