7712 W DAY ST 91042
Certificate Information: 7712 W DAY ST 91042
- Application / Permit
- 22014-20000-00790
- Plan Check / Job No.
- B22VN02690
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION ( 24'-9" X 15'-6" ) TO FRONT OF EX. SFD. EXPAND LIVING ROOM/ ENTRY. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/23/2022
- Issuing Office
- Current Status
- CofO Issued on 8/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2022 | ROSENDO MEDINA |
| Corrections Issued | 2/26/2022 | ROSENDO MEDINA |
| Applicant returned to address corrections | 4/5/2022 | ROSENDO MEDINA |
| Plan Check Approved | 4/11/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Issued | 4/23/2022 | APPLICANT |
| CofO in Progress | 6/21/2023 | DAVID ANDERSON |
| CofO Issued | 8/10/2023 | RUBEN SALAS |
| Permit Finaled | 8/10/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 3/2/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 3/23/2022 | MANUEL TEJADA |
Contact Information
| Contractor | 1 Oak Remodeling; Lic. No.: 1015424-B | 6320 VAN NUYS BLVD STE 305 VAN NUYS, CA 91401 |
| Engineer | Sabzehzar,, Habib; Lic. No.: C50442 | 8180 N PRICE AVE FRESNO, CA 93720 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/12/2022 | Corrections Issued | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 6/21/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Conditional Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Approved | DAVID ANDERSON |
| Insulation | 8/16/2022 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/27/2022 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 12/27/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 12/27/2022 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 12/27/2022 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 12/27/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Wood Frame | 12/27/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/1/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 2/1/2023 | Approved | DAVID ANDERSON |
| Pre-Inspection | 2/1/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 2/1/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/17/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/17/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/17/2023 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 2/17/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 2/17/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/27/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/2/2023 | Partial Approval | DAVID ANDERSON |
| Shower Pan | 3/2/2023 | Approved | DAVID ANDERSON |
| Insulation | 3/16/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 3/23/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/8/2023 | Approved | DAVID ANDERSON |
| Final | 5/8/2023 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 5/8/2023 | Approved | DAVID ANDERSON |
| Green Building Final | 5/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 5/8/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 5/8/2023 | Corrections Issued | DAVID ANDERSON |
| Final | 5/17/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 5/17/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 5/17/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 6/20/2023 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 6/20/2023 | Approved | DAVID ANDERSON |
| Smoke Detectors | 6/20/2023 | Approved | DAVID ANDERSON |