534 N BRONSON AVE 90004

Certificate Information: 534 N BRONSON AVE 90004

Application / Permit
22014-20000-00787
Plan Check / Job No.
B22VN02687
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE AND TWO STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLLING WITH MAJOR REMODEL; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/7/2022
Issuing Office
Valley
Current Status
Issued on 10/7/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 SELLA BENYAMIN
Corrections Issued 3/8/2022 SELLA BENYAMIN
Quality Review Completed 3/10/2022 STEVEN KIM
Building Plans Picked Up 3/16/2022 APPLICANT
Plan Check Approved 10/4/2022 SELLA BENYAMIN
Issued 10/7/2022 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 9/19/2022 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 9/21/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 9/21/2022 JEANIE LAM
Sewer availability Cleared 9/21/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/30/2023 Partial Approval JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 9/5/2023 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 9/8/2023 Approved JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 11/16/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 11/28/2023 Partial Inspection JEFFREY MEAD
PLUMBING-Rough 11/28/2023 Partial Approval JEFFREY MEAD
Insulation 12/8/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Partial Approval JEFFREY MEAD
Green Building Rough 12/14/2023 Not Ready for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Partial Approval JEFFREY MEAD
Deputy Drilled-In Anchors 3/6/2024 Partial Approval JEFFREY MEAD
Deputy Steel/Welding 3/6/2024 Partial Approval JEFFREY MEAD
Deputy Wood Construction 3/6/2024 Approved JEFFREY MEAD
Footing/Foundation/Slab 3/7/2024 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 3/8/2024 Conditional Approval JOSEPH MCGARRY
Green Building Rough 3/8/2024 Not Ready for Inspection JOSEPH MCGARRY
Special/Order Compliance 3/19/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 4/19/2024 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 4/19/2024 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 5/29/2024 Approved JEFFREY MEAD
HVAC-Rough 5/29/2024 Corrections Issued JEFFREY MEAD
Green Building Rough 6/4/2024 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 6/4/2024 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 6/10/2024 Corrections Issued JEFFREY MEAD
Green Building Rough 6/10/2024 Approved JEFFREY MEAD
PLUMBING-Rough 6/10/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 6/28/2024 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 7/10/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 7/10/2024 Approved JEFFREY MEAD
Insulation 8/13/2024 Conditional Approval NICHOLAS LOPEZ
Drywall Nailing 10/4/2024 Approved ANTHONY RAMOS
Insulation 10/4/2024 Approved ANTHONY RAMOS
Shower Pan 10/4/2024 Not Ready for Inspection ANTHONY RAMOS
Shower Pan 10/16/2024 Approved JEFFREY MEAD
Deputy Drilled-In Anchors 10/24/2024 Partial Approval JEFFREY MEAD
Interior/Exterior Lathing 1/22/2025 Approved JEFFREY MEAD
Deputy Wood Construction 5/22/2025 Conditional Approval JEFFREY MEAD
ELECTRICAL-Final 10/29/2025 Not Ready for Inspection JOSH MEISTER
ELECTRICAL-Final 1/9/2026 Corrections Issued JEFFREY MEAD
PLUMBING-Final 1/9/2026 Not Ready for Inspection JEFFREY MEAD
Smoke Detectors 1/9/2026 Approved JEFFREY MEAD
ELECTRICAL-Final 2/19/2026 Not Ready for Inspection JEFFREY MEAD
HVAC-Final 2/19/2026 Partial Inspection JEFFREY MEAD
PLUMBING-Final 2/19/2026 Approved JEFFREY MEAD
Service/Power Release 2/19/2026 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Final 2/24/2026 Not Ready for Inspection JEFFREY MEAD
Service/Power Release 2/24/2026 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Final 3/3/2026 Approved JEFFREY MEAD
Gas Test 3/3/2026 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 3/3/2026 SGSOV Not Ready JEFFREY MEAD
Service/Power Release 3/3/2026 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved JEFFREY MEAD
Final 4/22/2026 Not Ready for Inspection JEFFREY MEAD
Footing/Foundation/Slab 4/22/2026 Approved JEFFREY MEAD
Green Building Final 4/22/2026 Approved JEFFREY MEAD
Final 5/1/2026 Not Ready for Inspection JEFFREY MEAD
Final 5/12/2026 Corrections Issued JEFFREY MEAD