3122 N VERDUGO PL 90065

Certificate Information: 3122 N VERDUGO PL 90065

Application / Permit
22014-20000-00786
Plan Check / Job No.
B22VN02681
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION TO (E) SFD - 1 OF 2
Permit Issued
Issued on 8/2/2024
Issuing Office
Metro
Current Status
Issued on 8/2/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 CRYSTEL MAALOUF
Corrections Issued 5/3/2022 CRYSTEL MAALOUF
Quality Review Completed 5/4/2022 CHAD DOI
Building Plans Picked Up 5/6/2022 APPLICANT
Applicant returned to address corrections 8/29/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 12/14/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 8/15/2023 CRYSTEL MAALOUF
Applicant returned to address corrections 8/23/2023 CRYSTEL MAALOUF
Applicant returned to address corrections 9/7/2023 CRYSTEL MAALOUF
Applicant returned to address corrections 9/27/2023 CRYSTEL MAALOUF
Applicant returned to address corrections 3/12/2024 CRYSTEL MAALOUF
Plan Check Approved 6/25/2024 MAHNAZ NOURHASHEMI
Issued 8/2/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 5/19/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/2/2022 JEANIE LAM
Specific Plan Cleared 2/29/2024 RUBEN VASQUEZ
Grading Pre-Inspection Cleared 6/25/2024 CRYSTEL MAALOUF

Contact Information

Contractor Moriah Remodeling & Construction Inc; Lic. No.: 998852-B 9131 OAKDALE AVE SUITE #100      CHATSWORTH, CA 91311
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 11/7/2024 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 11/7/2024 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 11/7/2024 Partial Approval THOMAS LOGRASSO
Wood Frame 11/7/2024 Not Ready for Inspection THOMAS LOGRASSO
Wood Frame 11/12/2024 Partial Approval THOMAS LOGRASSO
Drywall Nailing 11/14/2024 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 11/22/2024 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 12/20/2024 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 12/31/2024 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 1/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Insulation 1/10/2025 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 2/4/2025 Partial Approval THOMAS LOGRASSO
Sewer 2/4/2025 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 2/13/2025 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 2/19/2025 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 2/24/2025 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 2/24/2025 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 2/24/2025 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 2/25/2025 Conditional Approval WILLIAM SIERRA
ELECTRICAL-Rough 2/27/2025 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Approved NICHOLAS LOPEZ
Green Building Rough 2/27/2025 Not Ready for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 3/5/2025 Partial Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 3/5/2025 Approved NICHOLAS LOPEZ
Green Building Rough 3/5/2025 Partial Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 3/5/2025 Partial Approval NICHOLAS LOPEZ
Insulation 3/24/2025 Partial Approval NICHOLAS LOPEZ
Drywall Nailing 3/26/2025 Partial Approval REGINA MENDEZ
BUILDING-Rough-Frame 4/22/2025 Partial Approval NICHOLAS LOPEZ
Green Building Rough 4/22/2025 Approved NICHOLAS LOPEZ
Insulation 4/24/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 5/5/2025 Approved NICHOLAS LOPEZ
Shower Pan 5/5/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 5/22/2025 Approved REGINA MENDEZ
Shower Pan 5/22/2025 Not Ready for Inspection REGINA MENDEZ
Smoke Detectors 7/23/2025 Corrections Issued NICHOLAS LOPEZ
BUILDING-Rough-Frame 8/1/2025 Approved ALIZAH MAYAGOITIA
Final 8/1/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/1/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 8/1/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 8/1/2025 Approved ALIZAH MAYAGOITIA
Final 9/15/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 9/15/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Approved NICHOLAS LOPEZ