107 1/4 S FLORES ST 90048

Certificate Information: 107 1/4 S FLORES ST 90048

Application / Permit
22014-20000-00785
Plan Check / Job No.
B22VN02679
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DEMO PORTION OF (E) DET. 4-CAR GARAGE AND CONVERT THE REMAINING TO NEW ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33 (c)-(d)] w/ ADDITION TO 1ST FLOOR AND NEW 2ND FLOOR ADDITION; NEW DIMENSION IS IRR. SHAPED 25'-10" x 29'-1"
Permit Issued
Issued on 9/8/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 SEAN SHAHMIRI
Corrections Issued 4/14/2022 SEAN SHAHMIRI
Quality Review Completed 4/15/2022 OMID HEDAYAT
Building Plans Picked Up 4/20/2022 APPLICANT
Plan Check Approved 8/15/2022 SEAN SHAHMIRI
Issued 9/8/2022 APPLICANT
CofO in Progress 6/7/2024 MEL KHACHATOURIAN
Permit Finaled 6/13/2024 DANIEL ORRANTE
CofO Issued 6/13/2024 DANIEL ORRANTE
Permit Finaled 6/13/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/21/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 4/21/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/25/2022 TREVOR QUAN
Sewer availability Cleared 5/25/2022 TREVOR QUAN
Construction near power lines Cleared 7/27/2022 RIDWAN HARDY

Contact Information

Contractor Revah Construction Inc; Lic. No.: 721980-B 177 S MARTEL AVE      LOS ANGELES, CA 90036
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/1/2023 Approved JEREMY TODD
METHANE-Barrier 2/1/2023 Approved JEREMY TODD
METHANE-Subgrade 2/1/2023 Approved JEREMY TODD
PLUMBING-Rough 2/1/2023 Approved JEREMY TODD
Wood Frame 2/17/2023 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 2/23/2023 Partial Approval JEREMY TODD
Deputy Wood Construction 2/23/2023 Approved JEREMY TODD
Green Building Rough 2/23/2023 Not Ready for Inspection JEREMY TODD
METHANE-Rough 2/23/2023 Not Ready for Inspection JEREMY TODD
Deputy Wood Construction 3/8/2023 Conditional Approval JEREMY TODD
Deputy Drilled-In Anchors 3/9/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Approved JEREMY TODD
Deputy Drilled-In Anchors 3/10/2023 Conditional Approval DAVID FEILER
HVAC-Rough 4/13/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Approved JEREMY TODD
Insulation 5/19/2023 Approved JEREMY TODD
Shower Pan 5/19/2023 Approved JEREMY TODD
Drywall Nailing 5/30/2023 Approved JEREMY TODD
Green Building Rough 5/30/2023 Approved JEREMY TODD
Interior/Exterior Lathing 5/30/2023 Approved JEREMY TODD
Interior/Exterior Lathing 6/7/2023 Approved JEREMY TODD
PLUMBING-Rough 7/13/2023 Not Ready for Inspection ARAM AVEDISIAN
Sewer 7/13/2023 Not Ready for Inspection ARAM AVEDISIAN
Special/Order Compliance 9/8/2023 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 2/13/2024 Approved MEL KHACHATOURIAN
Final 2/13/2024 Corrections Issued MEL KHACHATOURIAN
Green Building Final 2/13/2024 Approved MEL KHACHATOURIAN
METHANE-Final 2/13/2024 Approved MEL KHACHATOURIAN
METHANE-Rough 2/13/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 2/13/2024 Approved MEL KHACHATOURIAN
HVAC-Final 3/18/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Approved MEL KHACHATOURIAN
Final 5/30/2024 Not Ready for Inspection MEL KHACHATOURIAN
Final 6/3/2024 OK to Issue CofO MEL KHACHATOURIAN