14254 W SAYRE ST 91342

Certificate Information: 14254 W SAYRE ST 91342

Application / Permit
22014-20000-00780
Plan Check / Job No.
B22VN02666
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21' X 31' DETACHED GARAGE AND ADD 6'-5" X 18'-9" TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 8/4/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/22/2022 APPLICANT
Assigned to Plan Check Engineer 2/25/2022 RAPHAEL ROSAS
Corrections Issued 2/26/2022 RAPHAEL ROSAS
Applicant returned to address corrections 6/17/2022 RAPHAEL ROSAS
Plan Check Approved 7/17/2022 RAPHAEL ROSAS
Building Plans Picked Up 7/18/2022 APPLICANT
Issued 8/4/2022 APPLICANT
CofO in Progress 4/3/2024 KEVIN BERBERYAN
Permit Finaled 4/9/2024 RUBEN SALAS
CofO Issued 4/9/2024 RUBEN SALAS
Permit Finaled 4/9/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/25/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/25/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 4/25/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/6/2022 ROMAN GUTIERREZ
Hold Cleared 10/14/2022 PRISCILLA RUIZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/20/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 10/25/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/14/2022 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Corrections Issued ARAM AVEDISIAN
Green Building Rough 12/14/2022 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 1/19/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Gas Test 1/19/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 1/19/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 1/19/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 1/19/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Underground Mechanical 1/19/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/10/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 2/10/2023 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 2/10/2023 Approved MATTHEW NELSON
HVAC-Rough 2/10/2023 Approved MATTHEW NELSON
PLUMBING-Rough 2/10/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 2/15/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/15/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 2/21/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/22/2023 Approved MICHEL ABAJAN
Insulation 2/27/2023 Approved ARAM AVEDISIAN
Drywall Nailing 3/14/2023 Approved MICHEL ABAJAN
Sewer 7/14/2023 Approved RAUL OLAGI
Final 9/18/2023 Corrections Issued KEVIN BERBERYAN
Final 12/1/2023 Conditional Approval KEVIN BERBERYAN
Green Building Final 12/1/2023 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 12/1/2023 Approved KEVIN BERBERYAN
Final 4/3/2024 OK to Issue CofO KEVIN BERBERYAN