14254 W SAYRE ST 91342
Certificate Information: 14254 W SAYRE ST 91342
- Application / Permit
- 22014-20000-00780
- Plan Check / Job No.
- B22VN02666
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 21' X 31' DETACHED GARAGE AND ADD 6'-5" X 18'-9" TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/4/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2022 | RAPHAEL ROSAS |
| Corrections Issued | 2/26/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/17/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 7/17/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Issued | 8/4/2022 | APPLICANT |
| CofO in Progress | 4/3/2024 | KEVIN BERBERYAN |
| Permit Finaled | 4/9/2024 | RUBEN SALAS |
| CofO Issued | 4/9/2024 | RUBEN SALAS |
| Permit Finaled | 4/9/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/25/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 4/25/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/6/2022 | ROMAN GUTIERREZ |
| Hold | Cleared | 10/14/2022 | PRISCILLA RUIZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/20/2022 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 10/25/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/14/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Rough | 12/14/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/19/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Gas Test | 1/19/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 1/19/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 1/19/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/19/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 1/19/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/10/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/10/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 2/10/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 2/10/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/10/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/15/2023 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/21/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/22/2023 | Approved | MICHEL ABAJAN |
| Insulation | 2/27/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 3/14/2023 | Approved | MICHEL ABAJAN |
| Sewer | 7/14/2023 | Approved | RAUL OLAGI |
| Final | 9/18/2023 | Corrections Issued | KEVIN BERBERYAN |
| Final | 12/1/2023 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Final | 12/1/2023 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 12/1/2023 | Approved | KEVIN BERBERYAN |
| Final | 4/3/2024 | OK to Issue CofO | KEVIN BERBERYAN |