10333 N PINYON AVE 91042

Certificate Information: 10333 N PINYON AVE 91042

Application / Permit
22014-20000-00779
Plan Check / Job No.
B22VN02663
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 146 sq.ft. New Bedroom, New Bathroom and Interior remodel
Permit Issued
Issued on 7/9/2022
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2022 APPLICANT
Assigned to Plan Check Engineer 3/8/2022 CARLOS MONTES
Corrections Issued 3/8/2022 CARLOS MONTES
Applicant returned to address corrections 6/8/2022 JOE VO
Plan Check Approved 7/8/2022 JOE VO
Issued 7/9/2022 APPLICANT
CofO in Progress 9/13/2022 MATTHEW NELSON
CofO Issued 2/16/2023 RONALD MYRICK
Permit Finaled 2/16/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 3/9/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/9/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/9/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 3/10/2022 SERGIO VALENZUELA
ZI Cleared 4/29/2022 JASON CHAN
Sewer availability Cleared 5/27/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/27/2022 ROMAN GUTIERREZ
Private sewage disp. approval Cleared 6/2/2022 KIRK LINKLATER
Specific Plan Cleared 6/15/2022 RUBEN VASQUEZ

Contact Information

Contractor L P Design & Construction; Lic. No.: 901296-B       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/14/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 7/18/2022 Approved DAVID ANDERSON
ELECTRICAL-Rough 7/19/2022 Partial Approval WILLIAM WREN
PLUMBING-Rough 7/19/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/22/2022 Partial Approval GREGG CUMMINGS
HVAC-Rough 7/22/2022 Corrections Issued GREGG CUMMINGS
Insulation 7/22/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 7/28/2022 Partial Approval MATTHEW NELSON
Drywall Nailing 7/28/2022 Approved MATTHEW NELSON
Green Building Rough 7/28/2022 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 8/8/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 8/8/2022 Approved MATTHEW NELSON
Green Building Rough 8/8/2022 Approved MATTHEW NELSON
Insulation 8/11/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 8/11/2022 Approved MATTHEW NELSON
Drywall Nailing 8/16/2022 Approved MATTHEW NELSON
Final 9/1/2022 Corrections Issued MATTHEW NELSON
Green Building Final 9/1/2022 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved MATTHEW NELSON
Smoke Detectors 9/1/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 9/12/2022 Approved MATTHEW NELSON
Final 9/12/2022 OK to Issue CofO MATTHEW NELSON
Green Building Final 9/12/2022 Approved MATTHEW NELSON
HVAC-Final 9/12/2022 Approved MATTHEW NELSON
PLUMBING-Final 9/12/2022 Approved MATTHEW NELSON