18751 W GAULT ST 91335
Certificate Information: 18751 W GAULT ST 91335
- Application / Permit
- 22014-20000-00762
- Plan Check / Job No.
- B22VN02630
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 19'-6" X 25'-3" ADDITION AND CONVERT DETACHED GARAGE / STORAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) ALL WORK PER ENGINEER
- Permit Issued
- Issued on 5/19/2022
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 3/21/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 4/20/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/18/2022 | DANIEL ABRAMYAN |
| Issued | 5/19/2022 | APPLICANT |
| Building Plans Picked Up | 5/19/2022 | APPLICANT |
| CofO in Progress | 8/31/2022 | JEFFREY BULL |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
| CofO Issued | 10/15/2022 | MICHAEL SMITH |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 3/23/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 3/31/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 4/21/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/24/2022 | Partial Inspection | MORRIS JACKSON |
| Underground Mechanical | 5/25/2022 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 5/31/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 5/31/2022 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 6/6/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/6/2022 | Partial Approval | VINCENT HANLEY |
| Sewer | 6/13/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 6/21/2022 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Approved | JEFFREY BULL |
| Green Building Rough | 6/21/2022 | Partial Approval | JEFFREY BULL |
| ELECTRICAL-Rough | 7/5/2022 | Partial Approval | JEFFREY BULL |
| HVAC-Rough | 7/5/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 7/5/2022 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 7/8/2022 | Approved | ROBERT GOLD |
| ELECTRICAL-Rough | 7/8/2022 | Approved | ROBERT GOLD |
| Green Building Rough | 7/8/2022 | Approved | ROBERT GOLD |
| Insulation | 7/8/2022 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 7/8/2022 | Partial Approval | ROBERT GOLD |
| PLUMBING-Rough | 7/8/2022 | Partial Approval | ROBERT GOLD |
| Shower Pan | 7/8/2022 | Approved | ROBERT GOLD |
| Drywall Nailing | 7/14/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 7/14/2022 | Approved | JEFFREY BULL |
| Underground Mechanical | 7/29/2022 | Not Ready for Inspection | JEFFREY BULL |
| Underground Mechanical | 8/2/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 8/5/2022 | Approved | JEFFREY BULL |
| Final | 8/5/2022 | Not Ready for Inspection | JEFFREY BULL |
| Footing/Foundation/Slab | 8/5/2022 | Approved | JEFFREY BULL |
| Green Building Final | 8/5/2022 | Approved | JEFFREY BULL |
| HVAC-Final | 8/5/2022 | Approved | JEFFREY BULL |
| PLUMBING-Final | 8/5/2022 | Partial Approval | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/5/2022 | SGSOV Not Ready | JEFFREY BULL |
| Smoke Detectors | 8/5/2022 | Approved | JEFFREY BULL |
| Final | 8/19/2022 | No Access for Inspection | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 8/19/2022 | SGSOV Not Ready | KRISTEN CAUSEY |
| Final | 8/30/2022 | OK to Issue CofO | JEFFREY BULL |
| PLUMBING-Final | 8/30/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/30/2022 | SGSOV Approved | JEFFREY BULL |