7414 N ETON AVE 91303
Certificate Information: 7414 N ETON AVE 91303
- Application / Permit
- 22014-20000-00758
- Plan Check / Job No.
- B22VN02621
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 0'-6" X 12'-6" ON FIRST FLOOR AND 20'-6" X 30'-6" TO SECOND FLOOR AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); REMOVE PORTION OF EXISTING GARAGE
- Permit Issued
- Issued on 6/15/2022
- Issuing Office
- Current Status
- CofO Issued on 11/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | SELLA BENYAMIN |
| Corrections Issued | 3/8/2022 | SELLA BENYAMIN |
| Quality Review Completed | 3/10/2022 | STEVEN KIM |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Plan Check Approved | 5/19/2022 | SELLA BENYAMIN |
| Issued | 6/15/2022 | APPLICANT |
| CofO in Progress | 10/12/2022 | STEVEN BACK |
| Permit Finaled | 11/15/2022 | JOHN JANSON |
| CofO Issued | 11/15/2022 | JOHN JANSON |
| Permit Finaled | 11/15/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/16/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 4/7/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 4/15/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/22/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 6/28/2022 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 7/11/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 7/11/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2022 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 8/23/2022 | Conditional Approval | STEVEN BACK |
| ELECTRICAL-Rough | 8/23/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 8/23/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 8/23/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 8/25/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 8/25/2022 | Approved | STEVEN BACK |
| Underground Mechanical | 8/25/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 8/30/2022 | Approved | STEVEN BACK |
| Green Building Rough | 8/30/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 8/30/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/30/2022 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 9/1/2022 | Not Ready for Inspection | STEVEN BACK |
| Insulation | 9/1/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 9/8/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/12/2022 | Approved | STEVEN BACK |
| Final | 10/12/2022 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 10/12/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 10/12/2022 | Approved | STEVEN BACK |