4956 N GAVIOTA AVE 91436
Certificate Information: 4956 N GAVIOTA AVE 91436
- Application / Permit
- 22014-20000-00731
- Plan Check / Job No.
- B22VN02523
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 14'-6" X24'-6" (355SF) OPEN TRELLIS ADDITION AT REAR OF (E) SFD, ADD 8'-1"X6'-10" (51SF) ENTRY PORCH, RESTUCCO EXTERIOR WALL FINISH, AND CHANGE OUT ALL DOOR AND WINDOWS.
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/30/2025
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | DAWN MC NULTY |
| Corrections Issued | 3/25/2022 | DAWN MC NULTY |
| Quality Review Completed | 4/5/2022 | STEVEN KIM |
| Building Plans Picked Up | 4/5/2022 | APPLICANT |
| Applicant returned to address corrections | 4/26/2022 | DAWN MC NULTY |
| Applicant returned to address corrections | 5/11/2022 | DAWN MC NULTY |
| Applicant returned to address corrections | 6/30/2022 | DAWN MC NULTY |
| Plan Check Approved | 7/1/2022 | DAWN MC NULTY |
| Issued | 4/22/2024 | APPLICANT |
| Permit Finaled | 6/30/2025 | THOMAS FINNILA |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/28/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/30/2022 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Shepphird,, William Reynolds; Lic. No.: C28818 | P O BOX 8446 CALABASAS, CA 91372 |
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 10/23/2024 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/24/2024 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 11/7/2024 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/24/2025 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/21/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Drywall Nailing | 3/21/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/21/2025 | Corrections Issued | THOMAS FINNILA |
| Final | 6/25/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 6/25/2025 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/30/2025 | Approved | THOMAS FINNILA |
| Drywall Nailing | 6/30/2025 | Approved | THOMAS FINNILA |
| Final | 6/30/2025 | Permit Finaled | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/30/2025 | Approved | THOMAS FINNILA |
| Green Building Final | 6/30/2025 | Approved | THOMAS FINNILA |
| Green Building Rough | 6/30/2025 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 6/30/2025 | Approved | THOMAS FINNILA |