9819 S DENKER AVE 90047
Certificate Information: 9819 S DENKER AVE 90047
- Application / Permit
- 22014-20000-00729
- Plan Check / Job No.
- B22VN02518
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1ST AND 2ND STORY ADDITION TO (E) GARAGE FOR NEW 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c)AND(d)
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | COLIN LOREDO |
| Corrections Issued | 3/18/2022 | COLIN LOREDO |
| Quality Review Completed | 4/4/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Applicant returned to address corrections | 5/5/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 9/11/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 10/24/2022 | MOHAMMAD ESMAILI |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 10/31/2024 | JOSE MACIAS |
| CofO Issued | 11/4/2024 | DEROLD HAUFF |
| Permit Finaled | 11/4/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2022 | JEANETTE VONG |
| Miscellaneous | Cleared | 4/22/2022 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/26/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 6/13/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 6/16/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 8/25/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/28/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 12/9/2022 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 12/30/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 12/30/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/4/2023 | Corrections Issued | ENRIQUE MIRELES |
| Deputy Wood Construction | 4/4/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/4/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 4/4/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 4/4/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 4/13/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 4/13/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 4/20/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 5/11/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 5/11/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/12/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/12/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/5/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 8/5/2024 | Corrections Issued | JOSE MACIAS |
| Final | 8/5/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 8/5/2024 | Approved | JOSE MACIAS |
| Green Building Final | 8/5/2024 | Approved | JOSE MACIAS |
| METHANE-Barrier | 8/5/2024 | Approved | JOSE MACIAS |
| METHANE-Subgrade | 8/5/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 8/5/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 8/5/2024 | Approved | JOSE MACIAS |
| Final | 10/21/2024 | OK to Issue CofO | JOSE MACIAS |