5748-5750 N WILLIS AVE 91411

Certificate Information: 5748-5750 N WILLIS AVE 91411

Application / Permit
22014-20000-00715
Plan Check / Job No.
B22VN02490
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 17' 6" X 20' 3" ATTACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 20' 6" X 27' 2" IRR.-SHAPE REAR ADDITION TO (E) SFD. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 6/23/2022
Issuing Office
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 GURUNATH NESARAJAH
Corrections Issued 2/28/2022 GURUNATH NESARAJAH
Plan Check Approved 6/3/2022 GURUNATH NESARAJAH
Building Plans Picked Up 6/7/2022 APPLICANT
Issued 6/23/2022 APPLICANT
CofO in Progress 5/7/2024 RYAN SALAZAR
Permit Finaled 5/15/2024 RUBEN SALAS
CofO Issued 5/15/2024 RUBEN SALAS
Permit Finaled 5/15/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/19/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/19/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 4/19/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/19/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Wan,, Jianhua Betty; Lic. No.: C76776 9456 FERNBURY ST      CYPRESS, CA 90630

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/30/2022 Approved RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 10/24/2022 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 10/31/2022 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 11/1/2022 Approved RICHARD DOCKUS
Wood Frame 11/17/2022 Partial Approval RICHARD DOCKUS
Insulation 11/28/2022 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Partial Approval JOHN COLEMAN
HVAC-Rough 2/8/2023 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 2/24/2023 Partial Approval RYAN SALAZAR
Green Building Rough 2/24/2023 Not Ready for Inspection RYAN SALAZAR
Rough-Elec/Plmb/HVAC 2/24/2023 Approved RYAN SALAZAR
Insulation 3/20/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/20/2023 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 3/28/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 4/6/2023 Partial Approval RYAN SALAZAR
Shower Pan 4/6/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/21/2023 Approved RYAN SALAZAR
PLUMBING-Rough 4/21/2023 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 4/22/2024 Approved RYAN SALAZAR
Final 4/22/2024 Partial Approval RYAN SALAZAR
Green Building Final 4/22/2024 Approved RYAN SALAZAR
Green Building Rough 4/22/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/22/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 4/22/2024 Approved RYAN SALAZAR
Service/Power Release 4/25/2024 Approved RYAN SALAZAR
Final 5/8/2024 OK to Issue CofO RYAN SALAZAR