15320 W RAYNETA DR 91403
Certificate Information: 15320 W RAYNETA DR 91403
- Application / Permit
- 22014-20000-00712
- Plan Check / Job No.
- B22VN02481
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 32' x 47'-6" 2-STORY ADDITION W/ ATT. 2-CAR GARAGE/STORAGE AND PATIO COVER TO (E) 2-STORY SINGLE FAMILY DWELLING AND INTERIOR REMODEL; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 2/26/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | SEAN SHAHMIRI |
| Corrections Issued | 3/17/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 3/25/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Applicant returned to address corrections | 5/28/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 11/23/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 2/9/2023 | SEAN SHAHMIRI |
| Issued | 2/26/2024 | APPLICANT |
| CofO in Progress | 8/8/2025 | JACK KARGODORIAN |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
| CofO Issued | 2/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 7/28/2022 | NATHAN ROMINE |
| Hydrant and Access approval | Cleared | 9/17/2022 | RUEL COLE |
| Low Impact Development | Cleared | 10/14/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 12/27/2022 | COLIN LOREDO |
Contact Information
| Contractor | Premier Property Developers Inc; Lic. No.: 942459-B | P O BOX 260618 ENCINO, CA 91426 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Engineer | Sadjadi,, Abdulreza; Lic. No.: C51812 | 1223 WILSHIRE BLVD #169 SANTA MONICA, CA 90403 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/29/2024 | Corrections Issued | THOMAS FINNILA |
| Grading Pre-Inspection | 4/2/2024 | Partial Inspection | THOMAS FINNILA |
| Piling/Pier/Caisson | 4/2/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/3/2024 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/8/2024 | Partial Approval | THOMAS FINNILA |
| Pre-Inspection | 4/10/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/11/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/18/2024 | Partial Inspection | THOMAS FINNILA |
| Underground Mechanical | 4/24/2024 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/29/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Piling/Pier/Caisson | 5/1/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 5/2/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/6/2024 | Approved | THOMAS FINNILA |
| Wood Frame | 5/17/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Partial Approval | JACK KARGODORIAN |
| Deputy Wood Construction | 6/17/2024 | Conditional Approval | DAVID MATSON |
| Wood Frame | 6/17/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Wood Construction | 7/9/2024 | Conditional Approval | DAVID MATSON |
| Wood Frame | 7/15/2024 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/9/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 8/9/2024 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 8/9/2024 | Approved | JACK KARGODORIAN |
| Service/Power Release | 8/9/2024 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 8/9/2024 | Approved | JACK KARGODORIAN |
| Gas Test | 8/16/2024 | Approved | DAVID MATSON |
| Service/Power Release | 8/16/2024 | Not Ready for Inspection | DAVID MATSON |
| Shower Pan | 8/16/2024 | Approved | DAVID MATSON |
| Insulation | 8/22/2024 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 8/29/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 1/31/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 1/31/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 1/31/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 1/31/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 2/4/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Smoke Detectors | 2/4/2025 | Approved | KEVIN BERBERYAN |