6221 N FARMDALE AVE 91606

Certificate Information: 6221 N FARMDALE AVE 91606

Application / Permit
22014-20000-00707
Plan Check / Job No.
B22VN02452
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT W/ ADDITION AND OUT OUTDOOR 1/2 BATH (36'-6"X20'-0" )
Permit Issued
Issued on 4/22/2022
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 MOHAMMAD ESMAILI
Corrections Issued 3/13/2022 MOHAMMAD ESMAILI
Plan Check Approved 4/21/2022 MOHAMMAD ESMAILI
Issued 4/22/2022 APPLICANT
CofO in Progress 4/18/2024 JOSE AVILA
Permit Finaled 5/29/2024 RUBEN SALAS
CofO Issued 5/29/2024 RUBEN SALAS
Permit Finaled 5/29/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/30/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 3/30/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/31/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/31/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/23/2023 Corrections Issued JOHN HAYES
Underground Mechanical 6/1/2023 Partial Approval JOHN HAYES
Footing/Foundation/Slab 6/13/2023 Corrections Issued JOHN HAYES
Piling/Pier/Caisson 6/13/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 6/21/2023 Approved RAUL OLAGI
Sewer 6/21/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 7/21/2023 Corrections Issued JOHN HAYES
Underground Mechanical 7/26/2023 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 7/31/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 7/31/2023 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/3/2023 Corrections Issued JOHN HAYES
Underground Mechanical 8/7/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 8/16/2023 Corrections Issued JOHN HAYES
Underground Mechanical 8/16/2023 Partial Approval JOHN HAYES
Underground Mechanical 8/23/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 9/12/2023 Approved JOHN HAYES
Interior/Exterior Lathing 10/13/2023 No Access for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Partial Approval JOHN HAYES
Interior/Exterior Lathing 10/25/2023 No Access for Inspection THOMAS FINNILA
Interior/Exterior Lathing 10/31/2023 Partial Approval RYAN SALAZAR
Special/Order Compliance 10/31/2023 Corrections Issued RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Corrections Issued CHRISTOPHER ROJAS
Insulation 11/20/2023 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 12/7/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/3/2024 Approved JOHN HAYES
BUILDING-Rough-Frame 3/4/2024 Approved JOHN HAYES
Final 3/4/2024 Corrections Issued JOHN HAYES
Green Building Final 3/4/2024 Approved JOHN HAYES
Green Building Rough 3/4/2024 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Approved JOHN HAYES
Smoke Detectors 3/4/2024 Approved JOHN HAYES
Final 3/22/2024 Corrections Issued JOHN HAYES
Final 4/17/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 5/15/2024 Approved JOSE AVILA