6221 N FARMDALE AVE 91606
Certificate Information: 6221 N FARMDALE AVE 91606
- Application / Permit
- 22014-20000-00707
- Plan Check / Job No.
- B22VN02452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT W/ ADDITION AND OUT OUTDOOR 1/2 BATH (36'-6"X20'-0" )
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/13/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 4/21/2022 | MOHAMMAD ESMAILI |
| Issued | 4/22/2022 | APPLICANT |
| CofO in Progress | 4/18/2024 | JOSE AVILA |
| Permit Finaled | 5/29/2024 | RUBEN SALAS |
| CofO Issued | 5/29/2024 | RUBEN SALAS |
| Permit Finaled | 5/29/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 3/30/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/31/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/23/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 6/1/2023 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 6/13/2023 | Corrections Issued | JOHN HAYES |
| Piling/Pier/Caisson | 6/13/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/21/2023 | Approved | RAUL OLAGI |
| Sewer | 6/21/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 7/21/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 7/26/2023 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/31/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 7/31/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 8/7/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 8/16/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 8/16/2023 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 8/23/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 9/12/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 10/13/2023 | No Access for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 10/25/2023 | No Access for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/31/2023 | Partial Approval | RYAN SALAZAR |
| Special/Order Compliance | 10/31/2023 | Corrections Issued | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Insulation | 11/20/2023 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/7/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/3/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | JOHN HAYES |
| Final | 3/4/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 3/4/2024 | Approved | JOHN HAYES |
| Green Building Rough | 3/4/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 3/4/2024 | Approved | JOHN HAYES |
| Final | 3/22/2024 | Corrections Issued | JOHN HAYES |
| Final | 4/17/2024 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 5/15/2024 | Approved | JOSE AVILA |