13362 W HARTLAND ST 91405

Certificate Information: 13362 W HARTLAND ST 91405

Application / Permit
22014-20000-00676
Plan Check / Job No.
B22VN02347
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRR. SHAPED ADDITION @ FRONT (129 SF), NEW PORCH (68 SF), ENCLOSE (E) PORCH, AND REMODEL (E) SINGLE FAMILY DWELLING; ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 8/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 SEAN SHAHMIRI
Corrections Issued 2/28/2022 SEAN SHAHMIRI
Building Plans Picked Up 3/1/2022 APPLICANT
Quality Review Completed 3/2/2022 OMID HEDAYAT
Applicant returned to address corrections 7/8/2022 SEAN SHAHMIRI
Plan Check Approved 8/25/2022 SEAN SHAHMIRI
Issued 8/29/2022 APPLICANT
CofO in Progress 5/12/2023 KIRK SANDERS
CofO Issued 5/12/2023 MICHAEL SMITH
Permit Finaled 5/12/2023 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 3/1/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 4/25/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 8/17/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/29/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 8/29/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren Krist; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2022 Approved RAFAEL CORTES
Deputy Drilled-In Anchors 9/26/2022 Conditional Approval RAFAEL CORTES
Footing/Foundation/Slab 9/27/2022 Corrections Issued RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 10/3/2022 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Corrections Issued CALEB MEISTER
Deputy Wood Construction 10/25/2022 Conditional Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Approved WILLIAM WREN
PLUMBING-Rough 11/9/2022 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 11/16/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 11/16/2022 Corrections Issued CALEB MEISTER
BUILDING-Rough-Frame 11/18/2022 Approved WILLIAM WREN
ELECTRICAL-Rough 11/18/2022 Approved WILLIAM WREN
Green Building Rough 11/18/2022 Approved WILLIAM WREN
HVAC-Rough 11/18/2022 Approved WILLIAM WREN
PLUMBING-Rough 11/18/2022 Approved WILLIAM WREN
Shower Pan 11/18/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 12/7/2022 Approved KIRK SANDERS
Insulation 12/12/2022 Approved KIRK SANDERS
Drywall Nailing 12/19/2022 Approved KIRK SANDERS
Interior/Exterior Lathing 12/19/2022 Approved KIRK SANDERS
ELECTRICAL-Final 4/26/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 4/26/2023 Approved KIRK SANDERS
Final 4/28/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 4/28/2023 Approved KIRK SANDERS
Green Building Final 4/28/2023 Approved KIRK SANDERS
HVAC-Final 4/28/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 4/28/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 4/28/2023 Approved KIRK SANDERS
Final 5/11/2023 OK to Issue CofO KIRK SANDERS