8241 N MORSE AVE 91605

Certificate Information: 8241 N MORSE AVE 91605

Application / Permit
22014-20000-00672
Plan Check / Job No.
B22VN02327
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(17'-8"x38'-2"), 500 SQFT ADDITION OF TWO NEW BEDROOMS TO (E) SFD PER WFPP
Permit Issued
Issued on 5/10/2022
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 PETER MOSESIAN
Corrections Issued 3/16/2022 PETER MOSESIAN
Quality Review Completed 4/6/2022 OMID HEDAYAT
Building Plans Picked Up 4/6/2022 APPLICANT
Plan Check Approved 5/10/2022 PETER MOSESIAN
Issued 5/10/2022 APPLICANT
CofO in Progress 11/18/2022 GREGG CUMMINGS
CofO Issued 12/10/2022 MICHAEL SMITH
Permit Finaled 12/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/24/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/24/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 4/22/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/26/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/24/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 8/3/2022 Corrections Issued WILLIAM WREN
Excavation/Setback/Form/Re-Bar 8/3/2022 Approved WILLIAM WREN
Footing/Foundation/Slab 8/3/2022 Approved WILLIAM WREN
Pre-Inspection 8/9/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 8/12/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 8/24/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 8/29/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Corrections Issued WILLIAM WREN
Insulation 8/31/2022 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/6/2022 Partial Approval DEANDRE HOFFMAN
Deputy Wood Construction 9/7/2022 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 9/9/2022 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval WILLIAM WREN
HVAC-Rough 9/9/2022 Approved WILLIAM WREN
PLUMBING-Rough 9/9/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 9/14/2022 Partial Approval MATTHEW NELSON
Insulation 9/14/2022 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 9/14/2022 Approved MATTHEW NELSON
Insulation 9/16/2022 Approved ASHLEY THOMPSON
Drywall Nailing 9/20/2022 Not Ready for Inspection WILLIAM WREN
Green Building Rough 9/20/2022 Not Ready for Inspection WILLIAM WREN
Drywall Nailing 10/14/2022 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 10/14/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 10/14/2022 Partial Approval GREGG CUMMINGS
Shower Pan 10/14/2022 Approved GREGG CUMMINGS
Drywall Nailing 10/25/2022 Approved GREGG CUMMINGS
Drywall Nailing 11/2/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 11/10/2022 Approved GREGG CUMMINGS
Final 11/10/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 11/10/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 11/10/2022 Approved GREGG CUMMINGS
ELECTRICAL-Final 11/17/2022 Approved GREGG CUMMINGS
Final 11/17/2022 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 11/17/2022 Approved GREGG CUMMINGS
PLUMBING-Final 11/17/2022 Approved GREGG CUMMINGS