8243 N MORSE AVE 91605
Certificate Information: 8243 N MORSE AVE 91605
- Application / Permit
- 22014-20000-00671
- Plan Check / Job No.
- B22VN02327
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 2 CAR GARAGE TO ADU W/2ND STORY ADDITION (20'-6"x30'-6"), 1200 SQFT PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | PETER MOSESIAN |
| Corrections Issued | 3/16/2022 | PETER MOSESIAN |
| Quality Review Completed | 4/6/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/6/2022 | APPLICANT |
| Plan Check Approved | 5/10/2022 | PETER MOSESIAN |
| Issued | 5/10/2022 | APPLICANT |
| CofO in Progress | 11/18/2022 | GREGG CUMMINGS |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
| CofO Issued | 12/10/2022 | MICHAEL SMITH |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/24/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/24/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 4/22/2022 | ANDRES COVARRUBIAS |
| Hydrant and Access approval | Cleared | 4/26/2022 | DWIGHT SANKEY |
| Roof/Waste drainage to street | Cleared | 4/26/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/24/2022 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/3/2022 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 8/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Pre-Inspection | 8/9/2022 | Partial Inspection | WILLIAM WREN |
| Special/Order Compliance | 8/9/2022 | Approved | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 8/12/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/12/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Corrections Issued | GREGG CUMMINGS |
| Deputy Wood Construction | 9/7/2022 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 9/7/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | ALAN MORELOS |
| Gas Test | 9/7/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 9/7/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/9/2022 | Conditional Approval | MICHEL ABAJAN |
| Green Building Rough | 9/9/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/9/2022 | Approved | MICHEL ABAJAN |
| Insulation | 9/14/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/14/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/19/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/4/2022 | Approved | WILLIAM WREN |
| Gas Test | 10/14/2022 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 10/14/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 10/14/2022 | Partial Approval | GREGG CUMMINGS |
| Gas Test | 10/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 10/21/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | GREGG CUMMINGS |
| Final | 11/2/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 11/2/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 11/2/2022 | Approved | GREGG CUMMINGS |
| Final | 11/10/2022 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 11/17/2022 | Approved | GREGG CUMMINGS |
| Final | 11/17/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 11/17/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 11/17/2022 | Approved | GREGG CUMMINGS |