Permit Issued
Issued on 5/12/2022
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 SERGIO MUNIZ
Corrections Issued 2/21/2022 SERGIO MUNIZ
Plan Check Approved 4/29/2022 SERGIO MUNIZ
Building Plans Picked Up 5/3/2022 APPLICANT
Issued 5/12/2022 APPLICANT
CofO in Progress 11/17/2022 JAVIER RAMOS JR
CofO Issued 11/19/2022 MICHAEL SMITH
Permit Finaled 11/19/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 4/19/2022 KHAING AYE
Roof/Waste drainage to street Cleared 4/20/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/21/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/17/2022 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/17/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 6/9/2022 Approved JAVIER RAMOS JR
Shower Pan 6/14/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/21/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/24/2022 Approved JAVIER RAMOS JR
HVAC-Rough 6/24/2022 Approved JAVIER RAMOS JR
Deputy Wood Construction 6/29/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/29/2022 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 7/6/2022 Approved CARLOS MATAMOROS
Green Building Rough 7/6/2022 Approved CARLOS MATAMOROS
Insulation 7/6/2022 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 7/6/2022 Approved CARLOS MATAMOROS
Insulation 7/13/2022 Approved ALAN MORELOS
Drywall Nailing 7/14/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 9/6/2022 Corrections Issued JAVIER RAMOS JR
HVAC-Final 9/6/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 10/6/2022 Approved JAVIER RAMOS JR
Final 10/6/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 10/6/2022 Approved JAVIER RAMOS JR
Green Building Final 10/6/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 10/6/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 10/6/2022 Approved JAVIER RAMOS JR
Final 11/17/2022 OK to Issue CofO JAVIER RAMOS JR