3416 S 11TH AVE 90018
Certificate Information: 3416 S 11TH AVE 90018
- Application / Permit
- 22014-20000-00653
- Plan Check / Job No.
- B22VN02268
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 32' x 24' IRR SHAPE ADDITION TO DWELLING ANDINTERIOR REMODEL PER ENGINEERING. REFRAME ENTIRE DWELLING. ENTIRE BLDG SHALL BE FIRE SPRINKLER W/ NFPA-13D. "COMPLY WITH DEPARTMENT ORDER effective date 01/25/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 7/19/2022
- Issuing Office
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | JEFFREY TANGONAN |
| Corrections Issued | 2/20/2022 | JEFFREY TANGONAN |
| Plan Check Approved | 6/8/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| Issued | 7/19/2022 | APPLICANT |
| CofO in Progress | 10/19/2023 | CALEB MEISTER |
| Permit Finaled | 10/24/2023 | DEROLD HAUFF |
| CofO Issued | 10/24/2023 | DEROLD HAUFF |
| Permit Finaled | 10/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2022 | WALLIE JONG |
| Sewer availability | Cleared | 4/27/2022 | WALLIE JONG |
| Metro Rail approval | Cleared | 5/11/2022 | JEFFREY TANGONAN |
| ZI | Cleared | 5/12/2022 | DANG NGUYEN |
| Low Impact Development | Cleared | 5/27/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 5/31/2022 | WALLIE JONG |
Contact Information
| Contractor | Tellez Builders Corporation; Lic. No.: 1048878-B | 11647 PEARWOOD COURT SYLMAR, CA 91342 |
| Engineer | Morales,, Carlos A; Lic. No.: C69972 | 38100 SAN MATEO AVE PALMDALE, CA 93551 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2022 | Conditional Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 9/13/2022 | Approved | STUART CHAPMAN |
| Grading Pre-Inspection | 9/13/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 9/19/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 9/20/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/7/2022 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/14/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/5/2022 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 12/5/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 12/5/2022 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/8/2022 | Approved | STUART CHAPMAN |
| Gas Test | 12/8/2022 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 12/8/2022 | Approved | STUART CHAPMAN |
| Insulation | 12/8/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 12/8/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 12/8/2022 | Approved | STUART CHAPMAN |
| Insulation | 12/15/2022 | Approved | MICHAEL LEWIS |
| Wood Frame | 12/21/2022 | No Access for Inspection | CALEB MEISTER |
| Wood Frame | 12/30/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 1/5/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 1/5/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 2/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| Gas Test | 2/22/2023 | Approved | CALEB MEISTER |
| Service/Power Release | 2/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 6/7/2023 | Approved | CALEB MEISTER |
| Final | 6/7/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 6/7/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 6/7/2023 | Approved | CALEB MEISTER |
| Final | 6/28/2023 | Conditional Approval | CALEB MEISTER |
| Green Building Final | 6/28/2023 | Approved | CALEB MEISTER |