8500 N HATILLO AVE 91306
Certificate Information: 8500 N HATILLO AVE 91306
- Application / Permit
- 22014-20000-00618
- Plan Check / Job No.
- B22VN02219
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (15'-6" x 7'-5" ) TO THE (E) SFD FOR FULL BATHROOM/ CLOSET. WORK PER WFPP.
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2022 | ROSENDO MEDINA |
| Corrections Issued | 2/14/2022 | ROSENDO MEDINA |
| Applicant returned to address corrections | 2/28/2022 | ROSENDO MEDINA |
| Plan Check Approved | 4/18/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Issued | 4/25/2022 | APPLICANT |
| CofO in Progress | 4/17/2023 | DAVID SCANTLIN |
| Permit Finaled | 1/9/2025 | JOHN JANSON |
| CofO Issued | 1/9/2025 | JOHN JANSON |
| Permit Finaled | 1/9/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 4/7/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 4/7/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/12/2022 | Partial Approval | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 7/19/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/3/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 9/16/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 9/16/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 9/30/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/7/2023 | Approved | DAVID SCANTLIN |
| Final | 2/7/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 2/7/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 2/7/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 2/7/2023 | Approved | DAVID SCANTLIN |
| Final | 2/8/2023 | Corrections Issued | DAVID SCANTLIN |
| Final | 4/14/2023 | OK to Issue CofO | DAVID SCANTLIN |