8341 N SHARP AVE 91352

Certificate Information: 8341 N SHARP AVE 91352

Application / Permit
22014-20000-00615
Plan Check / Job No.
B22VN02215
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15'11" X 28'11" IRREGULAR SHAPE ADDITION TO THE (E) SFD.
Permit Issued
Issued on 4/1/2022
Issuing Office
Current Status
CofO Issued on 5/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/16/2022 PINANK PATEL
Corrections Issued 2/16/2022 PINANK PATEL
Plan Check Approved 4/1/2022 PINANK PATEL
Issued 4/1/2022 APPLICANT
Building Plans Picked Up 4/6/2022 APPLICANT
CofO in Progress 5/8/2023 MATTHEW NELSON
Permit Finaled 5/8/2023 MICHAEL SMITH
CofO Issued 5/8/2023 MICHAEL SMITH
Permit Finaled 5/8/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/3/2022 MARKOS PEREZ-BRAN
Sewer availability Cleared 3/3/2022 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 3/9/2022 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/19/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 8/16/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/29/2022 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 8/29/2022 Partial Approval GREGG CUMMINGS
Insulation 8/31/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 9/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Deputy Wood Construction 9/7/2022 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 12/20/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Approved MATTHEW NELSON
HVAC-Rough 12/20/2022 Approved MATTHEW NELSON
PLUMBING-Rough 12/20/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/27/2022 Approved MATTHEW NELSON
Green Building Rough 12/27/2022 Approved MATTHEW NELSON
Insulation 1/19/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/19/2023 Approved MATTHEW NELSON
Drywall Nailing 2/1/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 5/3/2023 Approved MATTHEW NELSON
Final 5/3/2023 OK to Issue CofO MATTHEW NELSON
Green Building Final 5/3/2023 Approved MATTHEW NELSON
HVAC-Final 5/3/2023 Approved MATTHEW NELSON
PLUMBING-Final 5/3/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved MATTHEW NELSON
Smoke Detectors 5/3/2023 Approved MATTHEW NELSON