14659 W COHASSET ST 91405
Certificate Information: 14659 W COHASSET ST 91405
- Application / Permit
- 22014-20000-00609
- Plan Check / Job No.
- B22VN02198
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 20'-0" x 21'-0" ADDITION TO THE (E) DETACHED GARAGE FOR A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 8/19/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 2/24/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 7/24/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 7/26/2022 | APPLICANT |
| Issued | 8/19/2022 | APPLICANT |
| CofO in Progress | 9/3/2024 | VINCENT HANLEY |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
| CofO Issued | 9/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/1/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/2/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/7/2022 | Order to Comply Issued | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 12/19/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/19/2022 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 12/19/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/17/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/15/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/21/2023 | Approved | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | DAVID MATSON |
| HVAC-Rough | 7/21/2023 | Approved | DAVID MATSON |
| PLUMBING-Rough | 7/21/2023 | Approved | DAVID MATSON |
| Shower Pan | 7/21/2023 | Not Ready for Inspection | DAVID MATSON |
| Shower Pan | 9/19/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/25/2023 | Approved | DAVID ANDERSON |
| Gas Test | 10/25/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 10/25/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 10/25/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 10/25/2023 | Approved | DAVID ANDERSON |
| Wood Frame | 10/25/2023 | Approved | DAVID ANDERSON |
| Insulation | 11/21/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/21/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/18/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/18/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/22/2023 | Partial Approval | GREGG CUMMINGS |
| Final | 8/26/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 8/26/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 8/26/2024 | Approved | VINCENT HANLEY |
| Final | 9/3/2024 | OK to Issue CofO | VINCENT HANLEY |