722 N LAS PALMAS AVE 90038
Certificate Information: 722 N LAS PALMAS AVE 90038
- Application / Permit
- 22014-20000-00592
- Plan Check / Job No.
- B22VN02141
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- RELOCATE PATIO DOORS, REMODEL STAIRWAY, 393 SF 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING TO BECOME A 2-STORY. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Current Status
- CofO Issued on 7/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | COLIN LOREDO |
| Corrections Issued | 3/15/2022 | COLIN LOREDO |
| Quality Review Completed | 3/21/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Plan Check Approved | 4/29/2022 | COLIN LOREDO |
| Issued | 4/29/2022 | APPLICANT |
| CofO in Progress | 7/15/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 7/16/2023 | DEROLD HAUFF |
| CofO Issued | 7/16/2023 | DEROLD HAUFF |
| Permit Finaled | 7/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/29/2022 | CINDY QI |
| Sewer availability | Cleared | 3/29/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2022 | CINDY QI |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Karma Remodel & Development Inc; Lic. No.: 875130-B | 21610 VENTURA BLVD WOODLAND HILLS, CA 91364 |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/21/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 10/21/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Barrier | 10/21/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 10/21/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 10/27/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/27/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| METHANE-Barrier | 10/27/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 10/27/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 12/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 12/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 12/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 12/5/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 12/5/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Special/Order Compliance | 12/6/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 12/8/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 12/8/2022 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 12/8/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 12/21/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 12/22/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/5/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 1/5/2023 | Approved | JOAQUIN GREENOUGH |
| Insulation | 1/5/2023 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 1/5/2023 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 1/11/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 1/11/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 1/11/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/11/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 7/11/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/11/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 7/11/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/11/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 7/14/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 7/14/2023 | Partial Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 7/14/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 7/14/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 7/15/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |
| MERV13>=Final | 7/15/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/15/2023 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 7/15/2023 | Approved | JOAQUIN GREENOUGH |