4922 N VANALDEN AVE 91356

Certificate Information: 4922 N VANALDEN AVE 91356

Application / Permit
22014-20000-00582
Plan Check / Job No.
B22VN02087
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
8' X 12' ADDITION TO THE FIRST FLOOR OF EXISTING SINGLE FAMILY DWELLING; INTERIOR REMODEL;
Permit Issued
Issued on 4/29/2022
Issuing Office
Current Status
CofO in Progress on 1/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 SELLA BENYAMIN
Corrections Issued 3/8/2022 SELLA BENYAMIN
Quality Review Completed 3/17/2022 STEVEN KIM
Building Plans Picked Up 3/18/2022 APPLICANT
Plan Check Approved 4/29/2022 SELLA BENYAMIN
Issued 4/29/2022 APPLICANT
CofO in Progress 3/8/2024 JOHN KIDWELL
No Progress 1/15/2025 SEAN WIRCH
CofO in Progress 1/15/2025 SEAN WIRCH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/18/2022 CARLOS AGUILERA
Sewer availability Cleared 4/18/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/17/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 8/17/2022 Partial Approval DAVID SANDOVAL
Green Building Rough 8/17/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 8/17/2022 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 8/22/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 8/22/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 8/22/2022 Approved DAVID SANDOVAL
Underground Mechanical 8/22/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 8/24/2022 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 8/26/2022 Corrections Issued DAVID SANDOVAL
Interior/Exterior Lathing 8/30/2022 Corrections Issued DAVID SANDOVAL
Green Building Rough 9/1/2022 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 9/1/2022 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 9/6/2022 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 9/12/2022 Partial Approval DAVID SANDOVAL
Green Building Rough 9/12/2022 Not Ready for Inspection DAVID SANDOVAL
Insulation 9/30/2022 Approved DAVID SANDOVAL
Drywall Nailing 10/12/2022 Partial Approval JUSTIN HAWLEY
Drywall Nailing 10/20/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 10/20/2022 Partial Approval JESUS PINEDA
Shower Pan 10/20/2022 Partial Approval JESUS PINEDA
Drywall Nailing 10/28/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 10/28/2022 Partial Inspection DAVID SANDOVAL
Shower Pan 11/1/2022 Partial Inspection DAVID SANDOVAL
Wood Frame 12/29/2022 Partial Approval JEFFREY BULL
Interior/Exterior Lathing 1/6/2023 Approved DAVID SANDOVAL
PLUMBING-Rough 1/12/2023 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 1/13/2023 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 9/8/2023 Approved SEAN HAUPT
ELECTRICAL-Final 9/8/2023 Approved SEAN HAUPT
Final 9/8/2023 Corrections Issued SEAN HAUPT
Green Building Final 9/8/2023 Not Ready for Inspection SEAN HAUPT
Green Building Rough 9/8/2023 Approved SEAN HAUPT
HVAC-Final 9/8/2023 Approved SEAN HAUPT
PLUMBING-Final 9/8/2023 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Approved SEAN HAUPT
Smoke Detectors 9/8/2023 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Final 9/12/2023 Not Ready for Inspection SEAN HAUPT
Final 9/12/2023 Corrections Issued SEAN HAUPT
Green Building Final 9/12/2023 Not Ready for Inspection SEAN HAUPT
HVAC-Final 9/12/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Final 9/12/2023 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 9/12/2023 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Final 3/7/2024 Approved JOHN KIDWELL
Final 3/7/2024 OK to Issue CofO JOHN KIDWELL
Green Building Final 3/7/2024 Approved JOHN KIDWELL
PLUMBING-Final 3/7/2024 Approved JOHN KIDWELL
Smoke Detectors 3/7/2024 Approved JOHN KIDWELL