6939 N NESTLE AVE 91335

Certificate Information: 6939 N NESTLE AVE 91335

Application / Permit
22014-20000-00571
Plan Check / Job No.
B22VN02053
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 16' X 16' 4" TO (E) DETACHED 2-CAR GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 7/8/2022
Issuing Office
Current Status
CofO Issued on 11/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 GURUNATH NESARAJAH
Corrections Issued 2/21/2022 GURUNATH NESARAJAH
Plan Check Approved 6/19/2022 GURUNATH NESARAJAH
Building Plans Picked Up 6/22/2022 APPLICANT
Issued 7/8/2022 APPLICANT
CofO in Progress 10/20/2023 JEFFREY BULL
Permit Finaled 11/21/2023 JOHN JANSON
CofO Issued 11/21/2023 JOHN JANSON
Permit Finaled 11/21/2023 JOHN JANSON

Permit Application Clearance Information

ZI Cleared 3/22/2022 LOUIS ORTEGA
Address approval Cleared 3/23/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 3/23/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/25/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 4/25/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 5/2/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/31/2023 Approved JEFFREY BULL
Underground Mechanical 3/31/2023 Not Ready for Inspection JEFFREY BULL
Excavation/Setback/Form/Re-Bar 4/7/2023 Approved SEAN HAUPT
Special/Order Compliance 4/7/2023 Partial Inspection MORRIS JACKSON
Underground Mechanical 4/7/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 6/1/2023 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 6/1/2023 Approved JEFFREY BULL
Green Building Rough 6/1/2023 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 6/1/2023 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 6/1/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 6/9/2023 Approved JEFFREY BULL
Green Building Rough 6/9/2023 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 6/9/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 6/22/2023 Partial Approval JEFFREY BULL
Interior/Exterior Lathing 7/3/2023 Approved JEFFREY BULL
Pre-Inspection 8/3/2023 Not Ready for Inspection SEAN WIRCH
BUILDING-Rough-Frame 10/4/2023 Approved JEFFREY BULL
Final 10/4/2023 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 10/4/2023 Approved JEFFREY BULL
Green Building Final 10/4/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 10/4/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Gas Company JEFFREY BULL
Smoke Detectors 10/4/2023 Approved JEFFREY BULL
Final 10/20/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 10/20/2023 Approved JEFFREY BULL