6939 N NESTLE AVE 91335
Certificate Information: 6939 N NESTLE AVE 91335
- Application / Permit
- 22014-20000-00571
- Plan Check / Job No.
- B22VN02053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 16' X 16' 4" TO (E) DETACHED 2-CAR GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 7/8/2022
- Issuing Office
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 2/21/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/19/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Issued | 7/8/2022 | APPLICANT |
| CofO in Progress | 10/20/2023 | JEFFREY BULL |
| Permit Finaled | 11/21/2023 | JOHN JANSON |
| CofO Issued | 11/21/2023 | JOHN JANSON |
| Permit Finaled | 11/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 3/22/2022 | LOUIS ORTEGA |
| Address approval | Cleared | 3/23/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 3/23/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/25/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 4/25/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/31/2023 | Approved | JEFFREY BULL |
| Underground Mechanical | 3/31/2023 | Not Ready for Inspection | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 4/7/2023 | Approved | SEAN HAUPT |
| Special/Order Compliance | 4/7/2023 | Partial Inspection | MORRIS JACKSON |
| Underground Mechanical | 4/7/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/1/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 6/1/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 6/1/2023 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 6/1/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 6/1/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 6/9/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 6/9/2023 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 6/9/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 6/22/2023 | Partial Approval | JEFFREY BULL |
| Interior/Exterior Lathing | 7/3/2023 | Approved | JEFFREY BULL |
| Pre-Inspection | 8/3/2023 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | JEFFREY BULL |
| Final | 10/4/2023 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 10/4/2023 | Approved | JEFFREY BULL |
| Green Building Final | 10/4/2023 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 10/4/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Gas Company | JEFFREY BULL |
| Smoke Detectors | 10/4/2023 | Approved | JEFFREY BULL |
| Final | 10/20/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 10/20/2023 | Approved | JEFFREY BULL |