12640 W MARCO PL 90066
Certificate Information: 12640 W MARCO PL 90066
- Application / Permit
- 22014-20000-00532
- Plan Check / Job No.
- B22VN01897
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-0" X 14'-8" ADDITION W/ DECK ABOVE TO (E) SFD , RELOCATE LAUNDRY, REMODEL THE (E) KITCHEN AND TWO BATHROOMS AND CONVERT THE (E) BEDROOM INTO A (N) WALK IN CLOSET.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 2/12/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 3/14/2022 | ARTIN ZARUKIAN |
| Issued | 3/17/2022 | APPLICANT |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| CofO in Progress | 10/21/2023 | RICHARD STEINBACH |
| Permit Finaled | 10/24/2023 | DANIEL ORRANTE |
| CofO Issued | 10/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 2/16/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/16/2022 | MIGUEL GAMBOA |
| Grading Pre-Inspection | Cleared | 2/17/2022 | BRIAN MILLER |
| Sewer availability | Cleared | 2/17/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2022 | JENSON LEE |
| Specific Plan | Cleared | 2/22/2022 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 3/1/2022 | JENSON LEE |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Pacific Blue Construction Inc; Lic. No.: 902319-B | 16060 VENTURA BLVD #105-256 ENCINO, CA 91436 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| HVAC-Rough | 11/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 12/9/2022 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 12/22/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 12/22/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 12/22/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 12/22/2022 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 12/22/2022 | Partial Inspection | CLAYTON GRAHAM |
| Underground Mechanical | 12/22/2022 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/23/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/3/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 1/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/3/2023 | Approved | JESUS RODRIGUEZ |
| Structural Steel Frame | 1/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/20/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/10/2023 | Approved | EVAN COOPER |
| Green Building Rough | 2/10/2023 | Approved | EVAN COOPER |
| Insulation | 2/10/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 2/22/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/24/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 4/24/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/13/2023 | Approved | MICHAEL PELHAM |
| HVAC-Final | 9/13/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Final | 9/13/2023 | Corrections Issued | MICHAEL PELHAM |
| Final | 10/12/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/12/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 10/12/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 10/12/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/12/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/12/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 10/12/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/12/2023 | Approved | JESUS RODRIGUEZ |