19934 W SATICOY ST 91306
Certificate Information: 19934 W SATICOY ST 91306
- Application / Permit
- 22014-20000-00529
- Plan Check / Job No.
- B22VN01890
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED REC. ROOM AND ADD 13'-5" X 10' X 20' INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ADD 7'-3" X 18'-5" TRELLIS PATIO COVER. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/4/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | RAPHAEL ROSAS |
| Corrections Issued | 2/17/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 5/24/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Issued | 10/4/2022 | APPLICANT |
| CofO in Progress | 11/30/2023 | ALEXANDER HANDY |
| Permit Finaled | 2/26/2024 | JOHN JANSON |
| CofO Issued | 2/26/2024 | JOHN JANSON |
| Permit Finaled | 2/26/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 4/18/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/20/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Markarian,, Mardiros; Lic. No.: C53434 | 3814 VANALDEN AVE TARZANA, CA 91356 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/30/2022 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 11/30/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 12/30/2022 | Partial Approval | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 1/26/2023 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 2/2/2023 | Approved | ALEXANDER HANDY |
| Pre-Inspection | 2/13/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/9/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 5/9/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 5/9/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 5/9/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Partial Approval | HORACE FULTZ |
| Insulation | 5/16/2023 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 5/16/2023 | Partial Approval | HORACE FULTZ |
| Drywall Nailing | 6/5/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 6/12/2023 | Partial Approval | ALEXANDER HANDY |
| Shower Pan | 6/12/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/5/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 10/18/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 10/18/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 10/18/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 10/18/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 10/18/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/1/2023 | Approved | ALEXANDER HANDY |
| Final | 11/1/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 11/1/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 11/1/2023 | Approved | ALEXANDER HANDY |
| Final | 11/7/2023 | Corrections Issued | ALEXANDER HANDY |
| Special/Order Compliance | 11/7/2023 | Partial Inspection | SEAN WIRCH |
| Final | 11/21/2023 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Final | 11/29/2023 | Approved | ALEXANDER HANDY |
| Final | 11/29/2023 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 11/29/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 11/29/2023 | Approved | ALEXANDER HANDY |
| Service/Power Release | 11/29/2023 | Approved | ALEXANDER HANDY |