16313 W BLACKHAWK ST 91344

Certificate Information: 16313 W BLACKHAWK ST 91344

Application / Permit
22014-20000-00514
Plan Check / Job No.
B22VN01849
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
41'-8" X 29'-8" ADDITION TO THE (E) SFD.
Permit Issued
Issued on 8/18/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 SERGIO MUNIZ
Corrections Issued 2/21/2022 SERGIO MUNIZ
Applicant returned to address corrections 7/14/2022 SERGIO MUNIZ
Plan Check Approved 8/16/2022 SERGIO MUNIZ
Building Plans Picked Up 8/16/2022 APPLICANT
Issued 8/18/2022 APPLICANT
CofO in Progress 2/20/2024 JAVIER RAMOS JR
Permit Finaled 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 4/13/2022 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 4/20/2022 CARLOS AGUILERA
Sewer availability Cleared 4/20/2022 CARLOS AGUILERA
Low Impact Development Cleared 5/4/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 5/9/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Barragan,, Pedro; Lic. No.: C90531 329 N HUBBARD AVE      SAN FERNANDO, CA 91340

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/10/2023 Approved RAUL OLAGI
Service/Power Release 1/30/2023 Approved JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 3/6/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/13/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 3/31/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 5/4/2023 Corrections Issued JAVIER RAMOS JR
Green Building Rough 5/4/2023 Not Ready for Inspection JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 5/4/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/10/2023 Approved JAVIER RAMOS JR
Insulation 5/10/2023 Corrections Issued JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 5/10/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/17/2023 Approved JAVIER RAMOS JR
Drywall Nailing 5/17/2023 Approved JAVIER RAMOS JR
Green Building Rough 5/17/2023 Approved JAVIER RAMOS JR
Insulation 5/17/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/17/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 5/26/2023 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 5/26/2023 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 6/5/2023 Approved JAVIER RAMOS JR
Shower Pan 6/5/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 7/17/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 10/3/2023 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 10/3/2023 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 10/3/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 10/3/2023 Approved JAVIER RAMOS JR
Final 2/20/2024 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 2/20/2024 Approved JAVIER RAMOS JR
Green Building Final 2/20/2024 Approved JAVIER RAMOS JR