1600 S SPAULDING AVE 90019

Certificate Information: 1600 S SPAULDING AVE 90019

Application / Permit
22014-20000-00512
Plan Check / Job No.
B22VN01838
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND 2ND FLOOR ADDITION TO THE EXISTING SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/6/2022
Issuing Office
Current Status
CofO Issued on 11/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 COLIN LOREDO
Corrections Issued 3/10/2022 COLIN LOREDO
Quality Review Completed 3/16/2022 OMID HEDAYAT
Building Plans Picked Up 3/21/2022 APPLICANT
Plan Check Approved 6/6/2022 COLIN LOREDO
Issued 6/6/2022 APPLICANT
CofO in Progress 10/10/2023 JOSE AVILA
Permit Finaled 11/18/2023 DEROLD HAUFF
CofO Issued 11/18/2023 DEROLD HAUFF
Permit Finaled 11/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/16/2022 CELINA MORENO
Sewer availability Cleared 3/16/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/17/2022 CELINA MORENO

Contact Information

Contractor Modern Works Inc; Lic. No.: 1060919-B 13535 VENTURA BLVD SUITE 250      SHERMAN OAKS, CA 91423
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/27/2022 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 8/1/2022 Approved JOSE AVILA
Footing/Foundation/Slab 8/1/2022 Approved JOSE AVILA
METHANE-Barrier 8/1/2022 Approved JOSE AVILA
METHANE-Subgrade 8/1/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 8/18/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 8/18/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Rough 8/18/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Approved JOSE AVILA
PLUMBING-Rough 8/23/2022 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Approved JOSE AVILA
Insulation 8/26/2022 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Corrections Issued JOSE AVILA
Green Building Rough 10/21/2022 Not Ready for Inspection JOSE AVILA
Wood Frame 10/21/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Approval JOSE AVILA
Wood Frame 11/15/2022 Partial Approval JOSE AVILA
Deputy Wood Construction 11/17/2022 Approved JOSE AVILA
ELECTRICAL-Rough 11/22/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 11/22/2022 Corrections Issued CALEB MEISTER
ELECTRICAL-Rough 12/2/2022 Not Ready for Inspection JOSE AVILA
HVAC-Rough 12/2/2022 Approved JOSE AVILA
PLUMBING-Rough 12/2/2022 Approved JOSE AVILA
Insulation 12/19/2022 Approved JOSE AVILA
Interior/Exterior Lathing 12/19/2022 Approved JOSE AVILA
Shower Pan 12/19/2022 Approved JOSE AVILA
Drywall Nailing 12/23/2022 Approved JOSE AVILA
Green Building Rough 12/23/2022 Approved JOSE AVILA
Interior/Exterior Lathing 12/23/2022 Partial Approval JOSE AVILA
Sewer 4/7/2023 Approved JOSE AVILA
Gas Test 4/14/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 8/10/2023 Approved JOSE AVILA
HVAC-Final 8/10/2023 Corrections Issued JOSE AVILA
PLUMBING-Final 8/10/2023 Approved JOSE AVILA
Final 8/17/2023 Corrections Issued JOSE AVILA
Green Building Final 8/17/2023 Approved JOSE AVILA
HVAC-Final 8/17/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 8/17/2023 Approved JOSE AVILA
HVAC-Final 8/24/2023 Approved JOSE AVILA
Final 10/5/2023 OK to Issue CofO JOSE AVILA