1600 S SPAULDING AVE 90019
Certificate Information: 1600 S SPAULDING AVE 90019
- Application / Permit
- 22014-20000-00512
- Plan Check / Job No.
- B22VN01838
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 2ND FLOOR ADDITION TO THE EXISTING SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/6/2022
- Issuing Office
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | COLIN LOREDO |
| Corrections Issued | 3/10/2022 | COLIN LOREDO |
| Quality Review Completed | 3/16/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Plan Check Approved | 6/6/2022 | COLIN LOREDO |
| Issued | 6/6/2022 | APPLICANT |
| CofO in Progress | 10/10/2023 | JOSE AVILA |
| Permit Finaled | 11/18/2023 | DEROLD HAUFF |
| CofO Issued | 11/18/2023 | DEROLD HAUFF |
| Permit Finaled | 11/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/16/2022 | CELINA MORENO |
| Sewer availability | Cleared | 3/16/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2022 | CELINA MORENO |
Contact Information
| Contractor | Modern Works Inc; Lic. No.: 1060919-B | 13535 VENTURA BLVD SUITE 250 SHERMAN OAKS, CA 91423 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/27/2022 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 8/1/2022 | Approved | JOSE AVILA |
| METHANE-Barrier | 8/1/2022 | Approved | JOSE AVILA |
| METHANE-Subgrade | 8/1/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/18/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/18/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Rough | 8/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 8/23/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Approved | JOSE AVILA |
| Insulation | 8/26/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 10/21/2022 | Not Ready for Inspection | JOSE AVILA |
| Wood Frame | 10/21/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | JOSE AVILA |
| Wood Frame | 11/15/2022 | Partial Approval | JOSE AVILA |
| Deputy Wood Construction | 11/17/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 11/22/2022 | Corrections Issued | CALEB MEISTER |
| HVAC-Rough | 11/22/2022 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 12/2/2022 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 12/2/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 12/2/2022 | Approved | JOSE AVILA |
| Insulation | 12/19/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/19/2022 | Approved | JOSE AVILA |
| Shower Pan | 12/19/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 12/23/2022 | Approved | JOSE AVILA |
| Green Building Rough | 12/23/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/23/2022 | Partial Approval | JOSE AVILA |
| Sewer | 4/7/2023 | Approved | JOSE AVILA |
| Gas Test | 4/14/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/10/2023 | Approved | JOSE AVILA |
| HVAC-Final | 8/10/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 8/10/2023 | Approved | JOSE AVILA |
| Final | 8/17/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 8/17/2023 | Approved | JOSE AVILA |
| HVAC-Final | 8/17/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 8/17/2023 | Approved | JOSE AVILA |
| HVAC-Final | 8/24/2023 | Approved | JOSE AVILA |
| Final | 10/5/2023 | OK to Issue CofO | JOSE AVILA |