7901 N OSTROM AVE 91406

Certificate Information: 7901 N OSTROM AVE 91406

Application / Permit
22014-20000-00507
Plan Check / Job No.
B22VN01817
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
56 SQ. FT. ADDITION TO ENCLOSE EX. ROOF, ADD CANTILEVER OVERHANG AT REAR, AND INTERIOR REMODEL TO THE (E) DWELLLING. ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/17/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2022 APPLICANT
Assigned to Plan Check Engineer 2/16/2022 JEFFREY TANGONAN
Corrections Issued 2/17/2022 JEFFREY TANGONAN
Plan Check Approved 3/17/2022 JEFFREY TANGONAN
Building Plans Picked Up 3/21/2022 APPLICANT
Issued 8/17/2022 APPLICANT
CofO in Progress 5/3/2023 RAUL OLAGI
CofO Issued 5/3/2023 MICHAEL SMITH
Permit Finaled 5/3/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/1/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/2/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/2/2022 DAGOVERTO GUERRERO

Contact Information

Architect Song,, Michael; Lic. No.: C32566 5608 E PEABODY STREET      LONG BEACH, CA 90808
Contractor Cavalier Builders Inc; Lic. No.: 758563-B 6520 PLATT AVE #732      WEST HILLS, CA 91307
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/31/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 11/22/2022 Approved RAUL OLAGI
Insulation 11/22/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 12/14/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 12/14/2022 Not Ready for Inspection RAUL OLAGI
Green Building Rough 12/14/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 12/14/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 12/20/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 12/20/2022 Approved RAUL OLAGI
HVAC-Rough 12/20/2022 Approved RAUL OLAGI
PLUMBING-Rough 12/20/2022 Approved RAUL OLAGI
Green Building Rough 12/22/2022 Approved RAUL OLAGI
Insulation 12/22/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 12/22/2022 Approved RAUL OLAGI
Drywall Nailing 1/3/2023 Not Ready for Inspection RAUL OLAGI
Drywall Nailing 1/4/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 3/2/2023 Approved RAUL OLAGI
Final 3/2/2023 Corrections Issued RAUL OLAGI
Green Building Final 3/2/2023 Approved RAUL OLAGI
HVAC-Final 3/2/2023 Approved RAUL OLAGI
PLUMBING-Final 3/2/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/2/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 3/2/2023 Approved RAUL OLAGI
Final 5/3/2023 OK to Issue CofO RAUL OLAGI