7651 W KYLE ST 91042
Certificate Information: 7651 W KYLE ST 91042
- Application / Permit
- 22014-20000-00502
- Plan Check / Job No.
- B22VN01791
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 14' 6" X 6' 1" IRR.-SHAPE TO REAR OF (E) SFD, ADD 7' 2" X 28' 6" TO FRONT OF (E) SFD, REMODEL KITCHEN & ADD BATHROOM. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 6/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 3/5/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/4/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/19/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/2/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/24/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Issued | 6/7/2022 | APPLICANT |
| CofO in Progress | 1/30/2023 | WILLIAM WREN |
| CofO Issued | 2/4/2023 | MICHAEL SMITH |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/23/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/23/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/23/2022 | LEE GUILBEAUX |
| ZI | Cleared | 5/17/2022 | STEVEN WECHSLER |
| Grading Pre-Inspection | Cleared | 5/24/2022 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hanbali,, Amjad; Lic. No.: C42213 | 514 W COMMERCE AVE STE C PALMDALE, CA 93551 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2022 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/1/2022 | Approved | MATTHEW NELSON |
| Deputy Other (see comments) | 7/21/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Corrections Issued | MATTHEW NELSON |
| Deputy Wood Construction | 9/27/2022 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/4/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/4/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/4/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 10/19/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/19/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/31/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 10/31/2022 | Approved | MATTHEW NELSON |
| Final | 1/18/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 1/18/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 1/18/2023 | Approved | WILLIAM WREN |
| Final | 1/25/2023 | OK to Issue CofO | WILLIAM WREN |