9862 N ARLETA AVE 91331

Certificate Information: 9862 N ARLETA AVE 91331

Application / Permit
22014-20000-00498
Plan Check / Job No.
B22VN01779
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
IRREGULAR SHAPED 475 SQ. FT. ADDITION TO AND CONVERT THE (E) 204 SQ. FT. GARAGE AND THE 463 SQ. FT. REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 3/25/2022
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2022 APPLICANT
Assigned to Plan Check Engineer 2/15/2022 PETER MOSESIAN
Corrections Issued 2/15/2022 PETER MOSESIAN
Building Plans Picked Up 2/17/2022 APPLICANT
Issued 3/25/2022 APPLICANT
CofO in Progress 8/26/2022 MICHEL ABAJAN
Permit Finaled 2/4/2023 MICHAEL SMITH
CofO Issued 2/4/2023 MICHAEL SMITH
Permit Finaled 2/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/4/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/8/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/8/2022 DAGOVERTO GUERRERO
Address approval Cleared 3/24/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Richard C C; Lic. No.: S1371 19321 VANOWEN ST      RESEDA, CA 91335

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/7/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 4/11/2022 Approved MICHEL ABAJAN
METHANE-Barrier 4/11/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 4/11/2022 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 4/12/2022 No Access for Inspection MICHEL ABAJAN
PLUMBING-Rough 4/20/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 4/20/2022 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 5/26/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/31/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/31/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 5/31/2022 Approved MICHEL ABAJAN
METHANE-Rough 5/31/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 5/31/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 6/14/2022 Corrections Issued JENNIFER RABUCHIN
Insulation 6/14/2022 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 6/14/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Partial Inspection MICHEL ABAJAN
HVAC-Rough 6/17/2022 Approved MICHEL ABAJAN
Insulation 6/17/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/17/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/28/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 6/28/2022 Corrections Issued GREGG CUMMINGS
Drywall Nailing 6/29/2022 Approved ASHLEY THOMPSON
Pre-Inspection 8/10/2022 Partial Inspection MICHEL ABAJAN
Final 8/23/2022 Corrections Issued DEANDRE HOFFMAN
Green Building Final 8/23/2022 Not Ready for Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 8/23/2022 Approved DEANDRE HOFFMAN
Gas Test 8/25/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/26/2022 Approved MICHEL ABAJAN
Final 8/26/2022 OK to Issue CofO MICHEL ABAJAN
Green Building Final 8/26/2022 Approved MICHEL ABAJAN
HVAC-Final 8/26/2022 Approved MICHEL ABAJAN
PLUMBING-Final 8/26/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Approved MICHEL ABAJAN