4691 N ALONZO AVE 91316

Certificate Information: 4691 N ALONZO AVE 91316

Application / Permit
22014-20000-00491
Plan Check / Job No.
B22VN01751
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AT REAR (6'-6"x29') AND SIDE (IRR. SHAPED 13'-6"x 33') OF (E) ONE-STORY SINGLE FAMILY DWELLING, CONVERT PORTION OF (E) ATT. GARAGE (130.5 SF) TO HABITABLE AREA, AND INTERIOR REMODEL; ALL WORK PER ENG DESIGN
Permit Issued
Issued on 5/5/2022
Issuing Office
Current Status
CofO Issued on 12/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 SEAN SHAHMIRI
Corrections Issued 2/22/2022 SEAN SHAHMIRI
Quality Review Completed 2/24/2022 OMID HEDAYAT
Building Plans Picked Up 3/8/2022 APPLICANT
Applicant returned to address corrections 3/24/2022 SEAN SHAHMIRI
Plan Check Approved 5/5/2022 SEAN SHAHMIRI
Issued 5/5/2022 APPLICANT
CofO in Progress 2/8/2024 SEAN HAUPT
Permit Finaled 12/31/2024 JOHN JANSON
CofO Issued 12/31/2024 JOHN JANSON
Permit Finaled 12/31/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/15/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/15/2022 CARLOS AGUILERA
Sewer availability Cleared 3/15/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 4/29/2022 GREGORY HOERNER

Contact Information

Contractor Owner-Builder       ,
Engineer Abkarian,, Raffi; Lic. No.: C36027 18763 VINTAGE STREET      NORTHRIDGE, CA 91324

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/13/2022 Conditional Approval JUSTIN HAWLEY
Footing/Foundation/Slab 5/16/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 5/18/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 8/3/2022 Partial Approval DAVID SANDOVAL
HVAC-Rough 9/23/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 10/3/2022 Approved JEFFREY BULL
PLUMBING-Rough 10/17/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 10/20/2022 Approved DAVID SANDOVAL
Wood Frame 10/20/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 2/17/2023 Approved JUSTIN HAWLEY
Green Building Rough 2/17/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 2/17/2023 Partial Approval JUSTIN HAWLEY
Insulation 3/17/2023 Approved DAVID SANDOVAL
Drywall Nailing 4/4/2023 Approved SEAN HAUPT
Gas Test 9/21/2023 Approved JEFFREY PARD
Gas Test 9/22/2023 Not Ready for Inspection JOHN KIDWELL
Final 1/25/2024 Corrections Issued SEAN HAUPT
Green Building Final 1/25/2024 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Approved SEAN HAUPT
Smoke Detectors 1/25/2024 Approved SEAN HAUPT
Final 2/7/2024 OK to Issue CofO SEAN HAUPT