1136 N KENTER AVE 90049

Certificate Information: 1136 N KENTER AVE 90049

Application / Permit
22014-20000-00454
Plan Check / Job No.
B22VN01604
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INT. REMODEL TO (E) SFD WITH NEW ATT. TRELLIS
Permit Issued
Issued on 8/2/2022
Issuing Office
Metro
Current Status
Issued on 8/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/1/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 CRYSTEL MAALOUF
Corrections Issued 3/4/2022 CRYSTEL MAALOUF
Quality Review Completed 3/9/2022 SEAN DANG
Building Plans Picked Up 3/14/2022 APPLICANT
Applicant returned to address corrections 6/23/2022 CRYSTEL MAALOUF
Plan Check Approved 7/22/2022 CRYSTEL MAALOUF
Issued 8/2/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 5/20/2022 STEVEN JIN
GPI Written Notices Cleared 6/15/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 6/15/2022 CRYSTEL MAALOUF
Eng Process Fee Ord 176,300 Cleared 6/21/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Artech Construction; Lic. No.: 848955-B 1136 N-KENTER AVENUE      LOS ANGELES, CA 90049
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/17/2022 Approved JUAN VALENZUELA
Footing/Foundation/Slab 11/17/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 7/27/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 7/27/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/14/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/15/2023 Partial Approval CARLOS MATAMOROS
HVAC-Rough 12/15/2023 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 12/20/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 12/20/2023 Approved KEVIN SARGSYAN
HVAC-Rough 12/20/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 1/10/2024 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 1/12/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 1/12/2024 Partial Approval KEVIN SARGSYAN
Insulation 1/31/2024 Approved BEN MOLSTAD
Deputy Steel/Welding 3/29/2024 Conditional Approval KEVIN SARGSYAN
Shower Pan 4/25/2024 Not Ready for Inspection KEVIN SARGSYAN
Drywall Nailing 4/29/2024 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 4/29/2024 Approved KEVIN SARGSYAN
Drywall Nailing 5/7/2024 Approved KEVIN SARGSYAN
Pre-Inspection 5/15/2024 Not Ready for Inspection ARAM AVEDISIAN
Deputy Steel/Welding 5/28/2024 Conditional Approval KEVIN SARGSYAN
Deputy Steel/Welding 5/31/2024 Conditional Approval KEVIN SARGSYAN
Interior/Exterior Lathing 6/3/2024 Approved KEVIN SARGSYAN
Sewer 11/1/2024 Approved ARAM AVEDISIAN
Gas Test 11/5/2024 Partial Approval KEVIN SARGSYAN
Underground Mechanical 11/5/2024 Partial Approval KEVIN SARGSYAN
HVAC-Rough 11/22/2024 Approved KIRK SANDERS