6013 S ARLINGTON AVE 90043
Certificate Information: 6013 S ARLINGTON AVE 90043
- Application / Permit
- 22014-20000-00452
- Plan Check / Job No.
- B22VN01596
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE AND ADD 27'-6" X 35' IRREGULAR SHAPE TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/27/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | RAPHAEL ROSAS |
| Corrections Issued | 2/19/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 4/27/2022 | RAPHAEL ROSAS |
| Issued | 5/27/2022 | APPLICANT |
| Building Plans Picked Up | 6/6/2022 | APPLICANT |
| CofO in Progress | 10/6/2022 | ENRIQUE MIRELES |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
| CofO Issued | 11/19/2022 | DEROLD HAUFF |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 3/7/2022 | ABEL CASILLAS |
| Low Impact Development | Cleared | 3/30/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | ABEL CASILLAS |
| Construction near power lines | Cleared | 4/14/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Bravo Group Construction Co; Lic. No.: 1067972-B | 695 S SANTA FE AVE #435 LOS ANGELES, CA 90021 |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/8/2022 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 6/14/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/7/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/7/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 7/7/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 7/7/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/7/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 7/12/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 7/12/2022 | Partial Approval | HORACE FULTZ |
| Drywall Nailing | 7/15/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/3/2022 | Approved | ENRIQUE MIRELES |
| Shower Pan | 8/3/2022 | Approved | ENRIQUE MIRELES |
| Final | 9/6/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 9/6/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 9/6/2022 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/6/2022 | Approved | ENRIQUE MIRELES |
| Final | 10/5/2022 | OK to Issue CofO | ENRIQUE MIRELES |