17712 W VICTORY BLVD 91316
Certificate Information: 17712 W VICTORY BLVD 91316
- Application / Permit
- 22014-20000-00449
- Plan Check / Job No.
- B22VN01585
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 133 SF ADDITION
- Permit Issued
- Issued on 3/11/2022
- Issuing Office
- Current Status
- CofO Issued on 10/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2022 | JESSE ARELLANO |
| Corrections Issued | 2/8/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 2/23/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 3/10/2022 | JESSE ARELLANO |
| Issued | 3/11/2022 | APPLICANT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| CofO in Progress | 8/3/2022 | JEFFREY BULL |
| CofO in Progress | 8/3/2022 | JEFFREY BULL |
| Permit Finaled | 10/11/2022 | JOHN JANSON |
| CofO Issued | 10/11/2022 | JOHN JANSON |
| Permit Finaled | 10/11/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 2/9/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/9/2022 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 3/11/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/26/2022 | Corrections Issued | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 4/29/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/11/2022 | Partial Approval | VINCENT HANLEY |
| Insulation | 5/11/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 5/11/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/24/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/24/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/24/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | ROBERT GOLD |
| Green Building Rough | 5/27/2022 | Approved | ROBERT GOLD |
| Insulation | 5/27/2022 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 5/27/2022 | Partial Approval | ROBERT GOLD |
| Drywall Nailing | 6/13/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/13/2022 | Approved | JEFFREY PARD |
| Shower Pan | 6/13/2022 | Approved | JEFFREY PARD |
| Final | 8/2/2022 | OK to Issue CofO | JEFFREY BULL |
| Footing/Foundation/Slab | 8/2/2022 | Approved | JEFFREY BULL |
| Green Building Final | 8/2/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Approved | JEFFREY BULL |