9647 N ETIWANDA AVE 91325

Certificate Information: 9647 N ETIWANDA AVE 91325

Application / Permit
22014-20000-00447
Plan Check / Job No.
B22VN01578
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
26' 8" X 29' 4" IRR.-SHAPE ADDITION & REMODEL (E) SFD TO ENLARGE MASTER BEDROOM/BATHROOM/CLOSET AND ADD (1) BATHROOM. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 4/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2022 APPLICANT
Assigned to Plan Check Engineer 2/11/2022 GURUNATH NESARAJAH
Corrections Issued 2/12/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 4/12/2022 GURUNATH NESARAJAH
Plan Check Approved 5/12/2022 GURUNATH NESARAJAH
Building Plans Picked Up 5/13/2022 APPLICANT
Issued 5/18/2022 APPLICANT
CofO in Progress 12/1/2023 DAVID SCANTLIN
Permit Finaled 4/3/2025 JOHN JANSON
CofO Issued 4/3/2025 JOHN JANSON
Permit Finaled 4/3/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/25/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/5/2022 CARLOS AGUILERA

Contact Information

Contractor We Build Green Inc; Lic. No.: 1073455-B 24306 GILMORE ST      WEST HILLS, CA 91307
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/2/2022 Partial Approval JEFFREY PARD
Deputy Drilled-In Anchors 8/8/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 8/16/2022 Approved JEFFREY PARD
Deputy Wood Construction 9/15/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 11/10/2022 Approved JOHN KIDWELL
ELECTRICAL-Rough 11/10/2022 Approved JOHN KIDWELL
Green Building Rough 11/10/2022 Approved JOHN KIDWELL
HVAC-Rough 11/10/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 11/10/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 11/10/2022 Approved JOHN KIDWELL
Insulation 11/22/2022 Approved JOHN KIDWELL
Drywall Nailing 12/13/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/13/2022 Partial Approval JOHN KIDWELL
Final 11/20/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 11/20/2023 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 11/20/2023 Approved DAVID SCANTLIN
Final 11/30/2023 OK to Issue CofO DAVID SCANTLIN