10406 N AMBOY AVE 91331

Certificate Information: 10406 N AMBOY AVE 91331

Application / Permit
22014-20000-00446
Plan Check / Job No.
B22VN01544
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION TO (E) GARAGE AND CONVERT THE ENTIRE BUILDING TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 3/27/2022
Issuing Office
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2022 DANIEL YIP
Corrections Issued 2/3/2022 DANIEL YIP
Plan Check Approved 3/22/2022 DANIEL YIP
Issued 3/27/2022 APPLICANT
CofO in Progress 11/14/2023 MICHEL ABAJAN
Permit Finaled 2/7/2024 RUBEN SALAS
CofO Issued 2/7/2024 RUBEN SALAS
Permit Finaled 2/7/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/3/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 3/3/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/4/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/4/2022 DAGOVERTO GUERRERO
Clean Up Green Up Cleared 3/14/2022 MIGUEL GAMBOA
Construction near power lines Cleared 3/18/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/17/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 6/17/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 7/7/2022 Approved MICHEL ABAJAN
METHANE-Barrier 7/7/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 7/7/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/26/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/26/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 8/26/2022 Approved MICHEL ABAJAN
METHANE-Rough 8/26/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 8/26/2022 Approved MICHEL ABAJAN
Insulation 11/9/2022 Corrections Issued ARAM AVEDISIAN
Drywall Nailing 12/2/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 12/2/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 12/2/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 1/13/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/20/2023 Approved JOHN COLEMAN
ELECTRICAL-Final 4/3/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 4/3/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 4/3/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 4/3/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 4/3/2023 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 4/3/2023 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 4/3/2023 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 7/19/2023 Approved MICHEL ABAJAN
Final 7/19/2023 Corrections Issued MICHEL ABAJAN
HVAC-Final 7/19/2023 Approved MICHEL ABAJAN
PLUMBING-Final 7/19/2023 Approved MICHEL ABAJAN
Smoke Detectors 7/19/2023 Approved MICHEL ABAJAN
Final 11/14/2023 OK to Issue CofO MICHEL ABAJAN