6537 W 81ST ST 90045
Certificate Information: 6537 W 81ST ST 90045
- Application / Permit
- 22014-20000-00444
- Plan Check / Job No.
- B22VN01529
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL W/ (23'-7"x6'-6"), 152 SQFT FRONT PATIO COVER, W/1ST AND 2ND FLOOR ADDITION (2648 SQFT) TO THE (E) SFD, W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | PETER MOSESIAN |
| Corrections Issued | 3/4/2022 | PETER MOSESIAN |
| Quality Review Completed | 3/10/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Applicant returned to address corrections | 6/27/2022 | PETER MOSESIAN |
| Plan Check Approved | 7/19/2022 | PETER MOSESIAN |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 10/26/2023 | HERBERT GIRON |
| Permit Finaled | 11/3/2023 | DANIEL ORRANTE |
| CofO Issued | 11/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/24/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/31/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 6/5/2022 | EDUARDO HERMOSO |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 6/6/2022 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ghavimi,, Rassoul Daneshvar; Lic. No.: C48282 | 7007 SHADETREE LANE WEST HILLS, CA 91307 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/29/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 8/29/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 8/31/2022 | Partial Approval | HERBERT GIRON |
| Wood Frame | 8/31/2022 | Conditional Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 9/2/2022 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 9/2/2022 | Approved | BOBBY KEY |
| Service/Power Release | 9/2/2022 | Partial Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Rough | 10/11/2022 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 10/11/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 10/11/2022 | Corrections Issued | HERBERT GIRON |
| Deputy Wood Construction | 10/12/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 10/14/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 10/14/2022 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 10/14/2022 | Partial Approval | HERBERT GIRON |
| Shower Pan | 10/14/2022 | Not Ready for Inspection | HERBERT GIRON |
| Wood Frame | 10/18/2022 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/20/2022 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 10/20/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/1/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 11/1/2022 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Wood Construction | 11/3/2022 | Conditional Approval | HERBERT GIRON |
| Wood Frame | 11/4/2022 | Conditional Approval | HERBERT GIRON |
| Deputy Wood Construction | 11/7/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/10/2022 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 11/10/2022 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 11/10/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/16/2022 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 11/16/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/1/2022 | Partial Approval | HERBERT GIRON |
| Drywall Nailing | 12/1/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 12/1/2022 | Partial Approval | HERBERT GIRON |
| Insulation | 12/1/2022 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 12/16/2022 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/2/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 3/2/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 3/2/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 3/2/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 3/2/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/9/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/8/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/8/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 6/8/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/13/2023 | Approved | HERBERT GIRON |
| Green Building Final | 6/13/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 6/13/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 6/13/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/13/2023 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 6/13/2023 | Approved | HERBERT GIRON |
| Final | 8/1/2023 | Corrections Issued | HERBERT GIRON |
| Final | 9/8/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/8/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 9/8/2023 | Approved | HERBERT GIRON |
| Final | 10/10/2023 | Not Ready for Inspection | HERBERT GIRON |
| Final | 10/23/2023 | OK to Issue CofO | HERBERT GIRON |