10730-10732 N GERALD AVE 91344
Certificate Information: 10730-10732 N GERALD AVE 91344
- Application / Permit
- 22014-20000-00440
- Plan Check / Job No.
- B22VN01519
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* CONVERT (412 SF) PORTION OF (E) SFD TO JADU PER CA GC 65852.2(e)(1)(A) AND 65852.22 AND ADD (88 SF) TO (E) SFD. ALL CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Current Status
- CofO Issued on 6/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2022 | VIVIAN LAO |
| Corrections Issued | 2/3/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 5/5/2022 | VIVIAN LAO |
| Plan Check Approved | 6/29/2022 | VIVIAN LAO |
| Issued | 7/6/2022 | APPLICANT |
| CofO in Progress | 6/8/2023 | JAVIER RAMOS JR |
| CofO Issued | 6/9/2023 | MICHAEL SMITH |
| Permit Finaled | 6/9/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/7/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/7/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/7/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/10/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/13/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/13/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/13/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/19/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 10/21/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/21/2022 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 10/21/2022 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 11/28/2022 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 12/2/2022 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/7/2022 | Approved | JAVIER RAMOS JR |
| Wood Frame | 12/14/2022 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/20/2022 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 12/20/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/27/2022 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/27/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/27/2022 | Partial Approval | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 1/3/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 1/10/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 1/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 1/12/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/31/2023 | Approved | JAVIER RAMOS JR |
| Final | 3/31/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 3/31/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 3/31/2023 | Approved | JAVIER RAMOS JR |
| Final | 6/8/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 6/8/2023 | Approved | JAVIER RAMOS JR |