11440 W CLOVER AVE 90066

Certificate Information: 11440 W CLOVER AVE 90066

Application / Permit
22014-20000-00429
Plan Check / Job No.
B22VN01489
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
16'- 10" X 16' - 5" IRR.-SHAPE ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 5/4/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 GURUNATH NESARAJAH
Corrections Issued 2/21/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 1/30/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/6/2023 ANGELICA DAVE
Plan Check Approved 5/4/2023 DANIEL ABRAMYAN
Issued 5/4/2023 APPLICANT
CofO in Progress 1/3/2024 JESUS PINEDA
Permit Finaled 1/12/2024 DANIEL ORRANTE
CofO Issued 1/12/2024 DANIEL ORRANTE
Permit Finaled 1/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/12/2022 VASIL MIHALEV
Address approval Cleared 11/8/2022 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 11/8/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 11/29/2022 ANTHONY MAINEZ
Sewer availability Cleared 11/29/2022 ANTHONY MAINEZ
Specific Plan Cleared 12/5/2022 ROBERT SANCHEZ
ZI Cleared 12/9/2022 MAXFIELD VERMY
Construction near power lines Cleared 3/11/2023 RIDWAN HARDY

Contact Information

Contractor Dreamland Db Corp; Lic. No.: 1085534-B 19336 CALVERT ST      TARZANA, CA 91335
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/6/2023 Not Ready for Inspection JOHNNY MIRANDA
Pre-Inspection 6/6/2023 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/12/2023 Partial Approval JOHNNY MIRANDA
Underground Mechanical 6/12/2023 Partial Approval JOHNNY MIRANDA
Sewer 6/22/2023 Approved JOHNNY MIRANDA
Deputy Drilled-In Anchors 6/28/2023 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 7/3/2023 Corrections Issued JEREMY TODD
Footing/Foundation/Slab 7/11/2023 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 7/25/2023 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Partial Approval EVAN COOPER
Special/Order Compliance 7/25/2023 Corrections Issued EVAN COOPER
PLUMBING-Rough 8/1/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 8/16/2023 Approved JESUS PINEDA
HVAC-Rough 8/16/2023 Approved JESUS PINEDA
Shower Pan 8/24/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 9/5/2023 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 9/19/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 9/19/2023 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 10/16/2023 Approved JESUS PINEDA
Green Building Rough 10/16/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 10/16/2023 Approved JESUS PINEDA
Insulation 10/23/2023 Corrections Issued JESUS PINEDA
Insulation 10/26/2023 Approved JESUS PINEDA
Drywall Nailing 11/2/2023 Approved JESUS PINEDA
ELECTRICAL-Final 1/2/2024 Approved JESUS PINEDA
Final 1/2/2024 OK to Issue CofO JESUS PINEDA
Green Building Final 1/2/2024 Approved JESUS PINEDA
HVAC-Final 1/2/2024 Approved JESUS PINEDA
PLUMBING-Final 1/2/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 1/2/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 1/2/2024 Approved JESUS PINEDA