6172 N CLEON AVE 91606

Certificate Information: 6172 N CLEON AVE 91606

Application / Permit
22014-20000-00420
Plan Check / Job No.
B22VN01456
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
16.75'x17.08' ADDITION TO AND CONVERT THE (E) 379 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 5/31/2022
Issuing Office
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 2/25/2022 JESSE ARELLANO
Corrections Issued 2/26/2022 JESSE ARELLANO
Applicant returned to address corrections 4/15/2022 JESSE ARELLANO
Plan Check Approved 5/10/2022 JESSE ARELLANO
No Progress 5/10/2022 JESSE ARELLANO
Plan Check Approved 5/10/2022 JESSE ARELLANO
Building Plans Picked Up 5/11/2022 APPLICANT
Issued 5/31/2022 APPLICANT
CofO in Progress 10/18/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 10/22/2024 DANIEL ORRANTE
CofO Issued 10/22/2024 DANIEL ORRANTE
Permit Finaled 10/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 3/29/2022 WALTER RAMIREZ
Address approval Cleared 3/31/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 3/31/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/1/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/1/2022 DAGOVERTO GUERRERO
Green Code Cleared 4/19/2022 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/7/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 6/7/2023 Not Ready for Inspection JOHN HAYES
Sewer 6/7/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 6/13/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 6/13/2023 Not Ready for Inspection JOHN HAYES
Sewer 6/13/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 6/23/2023 Partial Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 6/23/2023 Not Ready for Inspection THOMAS FINNILA
Sewer 6/23/2023 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 7/7/2023 Approved DAVID MATSON
Footing/Foundation/Slab 7/7/2023 Approved DAVID MATSON
BUILDING-Rough-Frame 9/20/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 9/20/2023 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Partial Approval JOHN HAYES
HVAC-Rough 9/20/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 9/20/2023 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 9/20/2023 Corrections Issued JOHN HAYES
Sewer 9/20/2023 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 10/5/2023 Partial Approval JOHN HAYES
Special/Order Compliance 10/5/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 10/17/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 10/17/2023 Approved JOHN HAYES
Green Building Rough 10/17/2023 Approved JOHN HAYES
HVAC-Rough 10/17/2023 Approved JOHN HAYES
PLUMBING-Rough 10/17/2023 Approved JOHN HAYES
Special/Order Compliance 10/17/2023 Corrections Issued JOHN HAYES
Insulation 11/2/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 11/27/2023 No Access for Inspection MISAEL ESPARZA
Drywall Nailing 12/5/2023 Approved JOHN HAYES
ELECTRICAL-Rough 12/5/2023 Corrections Issued JOHN HAYES
PLUMBING-Final 4/10/2024 No Access for Inspection JOHN HAYES
Sewer 4/10/2024 No Access for Inspection JOHN HAYES
PLUMBING-Final 4/15/2024 Corrections Issued SALVADOR MARTINEZ
Sewer 4/15/2024 Partial Approval SALVADOR MARTINEZ
Underground Mechanical 4/15/2024 Approved SALVADOR MARTINEZ
Shower Pan 5/1/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/7/2024 Partial Approval JOHN HAYES
ELECTRICAL-Final 5/31/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 9/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 9/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 9/9/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 9/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 9/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 9/9/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 9/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 9/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 9/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 9/20/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/20/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/20/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 9/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 10/8/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Gas Test 10/8/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 10/8/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Final 10/18/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/18/2024 Approved ROBERTO PALACIOS-LOPEZ