7762 S ISIS AVE 90045

Certificate Information: 7762 S ISIS AVE 90045

Application / Permit
22014-20000-00405
Plan Check / Job No.
B22VN01415
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
17'-5" X 33' IRREG SHAPED ADDITION FOR NEW BEDROOM, BATHROOM, AND CLOSET. CONVERT (E) BATHROOM TO ENLARGE AND REMODEL KITCHEN.
Permit Issued
Issued on 3/29/2022
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/9/2022 JEROME MAGAT PALMA
Corrections Issued 2/9/2022 JEROME MAGAT PALMA
Plan Check Approved 3/16/2022 JEROME MAGAT PALMA
Building Plans Picked Up 3/21/2022 APPLICANT
Issued 3/29/2022 APPLICANT
CofO in Progress 1/12/2023 BOBBY KEY
Permit Finaled 1/19/2023 DANIEL ORRANTE
CofO Issued 1/19/2023 DANIEL ORRANTE
Permit Finaled 1/19/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/17/2022 JENSON LEE
Grading Pre-Inspection Cleared 2/17/2022 SERGIO VALENZUELA
Roof/Waste drainage to street Cleared 2/17/2022 JENSON LEE
Specific Plan Cleared 2/17/2022 VALERIA CEJA
Sewer availability Cleared 3/7/2022 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 1171 JUSTIN AVE APT 3      GLENDALE, CA 91201

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/14/2022 Approved BOBBY KEY
Footing/Foundation/Slab 4/14/2022 Corrections Issued BOBBY KEY
Excavation/Setback/Form/Re-Bar 4/21/2022 Approved BOBBY KEY
Footing/Foundation/Slab 4/21/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 4/29/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 7/12/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 7/12/2022 Approved JESUS RODRIGUEZ
Green Building Rough 7/12/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 7/12/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Approved BOBBY KEY
Green Building Rough 8/1/2022 Not Ready for Inspection BOBBY KEY
HVAC-Rough 8/1/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 8/1/2022 Approved BOBBY KEY
Insulation 8/15/2022 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 8/23/2022 Corrections Issued BOBBY KEY
Drywall Nailing 8/23/2022 Not Ready for Inspection BOBBY KEY
Green Building Rough 8/23/2022 Not Ready for Inspection BOBBY KEY
HVAC-Rough 8/23/2022 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 8/23/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 8/25/2022 Conditional Approval BOBBY KEY
Drywall Nailing 8/25/2022 Conditional Approval BOBBY KEY
Green Building Rough 8/25/2022 Approved BOBBY KEY
HVAC-Rough 8/25/2022 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 10/6/2022 Approved BOBBY KEY
Drywall Nailing 10/6/2022 Approved BOBBY KEY
HVAC-Rough 10/6/2022 Approved BOBBY KEY
Shower Pan 10/13/2022 Corrections Issued BOBBY KEY
Shower Pan 10/14/2022 No Access for Inspection BOBBY KEY
Shower Pan 10/19/2022 Approved BOBBY KEY
ELECTRICAL-Final 1/5/2023 Not Ready for Inspection HERBERT GIRON
Final 1/5/2023 Not Ready for Inspection HERBERT GIRON
Green Building Final 1/5/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Final 1/5/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/5/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/5/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/5/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 1/9/2023 Corrections Issued BOBBY KEY
Final 1/9/2023 Corrections Issued BOBBY KEY
HVAC-Final 1/9/2023 Approved BOBBY KEY
PLUMBING-Final 1/9/2023 Approved BOBBY KEY
Smoke Detectors 1/9/2023 Approved BOBBY KEY
ELECTRICAL-Final 1/12/2023 Approved BOBBY KEY
Final 1/12/2023 OK to Issue CofO BOBBY KEY
Green Building Final 1/12/2023 Approved BOBBY KEY