17107 W STRAWBERRY DR 91436
Certificate Information: 17107 W STRAWBERRY DR 91436
- Application / Permit
- 22014-20000-00383
- Plan Check / Job No.
- B22VN01344
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (551.3 S.F) ADDITION TO THE (E) SINGLE FAMILY DWELLING BY ENCLOSING THE (E) COURTYARD FOR A NEW GRAND ENTRANCE.
- Permit Issued
- Issued on 11/13/2025
- Issuing Office
- Valley
- Current Status
- Issued on 11/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 2/10/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 6/10/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 7/17/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 7/21/2022 | APPLICANT |
| Issued | 11/13/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/14/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/14/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/14/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/14/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/14/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/14/2022 | CARLOS AGUILERA |
| ZA Case | Cleared | 4/14/2022 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 5/3/2022 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 6/1/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christenson,, Paul Scott; Lic. No.: C57182 | 3529 COASTVIEW CT CARLSBAD, CA 92010 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Drywall Nailing | 6/10/2026 |
Inspection Request History
| Footing/Foundation/Slab | 3/17/2026 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/20/2026 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Partial Approval | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2026 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 5/13/2026 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/26/2026 | Approved | JUAN ALVARADO |
| Wood Frame | 5/26/2026 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Rough | 5/28/2026 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/28/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 5/28/2026 | Approved | THOMAS FINNILA |
| Insulation | 6/1/2026 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/8/2026 | Partial Approval | JOHN KIDWELL |