10339 N MONTGOMERY AVE 91344
Certificate Information: 10339 N MONTGOMERY AVE 91344
- Application / Permit
- 22014-20000-00377
- Plan Check / Job No.
- B22VN01328
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH GROUND AND 2ND STORY ADDITION TO CREATE A 2-STORY ADU PER LAMC 12.22 A.33 (c) AND (d)
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Current Status
- CofO Issued on 6/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | KHEDER ALRAZAA |
| Corrections Issued | 2/20/2022 | KHEDER ALRAZAA |
| Quality Review Completed | 3/1/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 11/18/2022 | KHEDER ALRAZAA |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 2/12/2024 | JAVIER RAMOS JR |
| CofO in Progress | 3/8/2024 | JAVIER RAMOS JR |
| CofO in Progress | 6/6/2024 | JAVIER RAMOS JR |
| No Progress | 6/14/2024 | ROBERT GOLD |
| CofO in Progress | 6/14/2024 | ROBERT GOLD |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
| CofO Issued | 6/21/2024 | RUBEN SALAS |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/15/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/18/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/2/2022 | TINA MIRANDA |
Contact Information
| Contractor | Alin Design Inc; Lic. No.: 878427-B | 16035 BLACKHAWK STREET GRANADA HILLS, CA 91344 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/19/2023 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 5/19/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 5/19/2023 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 5/25/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 5/30/2023 | Conditional Approval | MICHEL ABAJAN |
| Green Building Rough | 7/11/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Special/Order Compliance | 7/11/2023 | Corrections Issued | JAVIER RAMOS JR |
| Wood Frame | 7/11/2023 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/21/2023 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Partial Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 8/21/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/21/2023 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Wood Construction | 8/28/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/6/2023 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 10/6/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 10/6/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 10/6/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/6/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 10/13/2023 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 10/13/2023 | Not Ready for Inspection | ROBERT GOLD |
| Shower Pan | 10/13/2023 | Approved | ROBERT GOLD |
| Drywall Nailing | 10/25/2023 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/25/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/27/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 11/1/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/3/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/3/2024 | Partial Inspection | JAVIER RAMOS JR |
| Final | 1/3/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/3/2024 | Approved | JAVIER RAMOS JR |
| Green Building Final | 1/3/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/3/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/6/2024 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Final | 2/6/2024 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Final | 2/6/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Service/Power Release | 2/6/2024 | Not Required | JOHN COLEMAN |
| Special/Order Compliance | 2/6/2024 | No Access for Inspection | JOHN COLEMAN |
| ELECTRICAL-Final | 2/8/2024 | Approved | JAVIER RAMOS JR |
| Final | 2/8/2024 | Partial Inspection | JAVIER RAMOS JR |
| Green Building Final | 2/8/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/8/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/8/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 2/8/2024 | Approved | JAVIER RAMOS JR |
| Final | 3/11/2024 | Corrections Issued | JAVIER RAMOS JR |
| Special/Order Compliance | 3/12/2024 | Approved | JAVIER RAMOS JR |
| Special/Order Compliance | 5/6/2024 | Partial Approval | JAVIER RAMOS JR |
| Final | 6/5/2024 | OK to Issue CofO | JAVIER RAMOS JR |