8560 N VINEVALLEY DR 91352

Certificate Information: 8560 N VINEVALLEY DR 91352

Application / Permit
22014-20000-00361
Plan Check / Job No.
B22VN01280
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
3'-5" X 6'-7" & 8'-8" X 10'-8" ADDITION TO THE (E) SFD, AND INTERIOR REMODEL WITH WINDOW AND DOOR CHANGE OUT. ADD (N) 49'-10" X 35'-5" IRREGULUAR SHAPE PATIO COVER.
Permit Issued
Issued on 5/2/2022
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 SERGIO MUNIZ
Corrections Issued 2/5/2022 SERGIO MUNIZ
Applicant returned to address corrections 3/6/2022 SERGIO MUNIZ
Plan Check Approved 4/26/2022 SERGIO MUNIZ
Building Plans Picked Up 4/26/2022 APPLICANT
Issued 5/2/2022 APPLICANT
CofO in Progress 11/7/2022 DAVID ANDERSON
Permit Finaled 12/10/2022 MICHAEL SMITH
CofO Issued 12/10/2022 MICHAEL SMITH
Permit Finaled 12/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/22/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 3/29/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 4/7/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 4/26/2022 SERGIO MUNIZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/4/2022 Conditional Approval WILLIAM KUEHN
Footing/Foundation/Slab 5/6/2022 Partial Approval CHRISTOPHER DELLEFIELD
Underground Mechanical 5/6/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/26/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 5/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Rough-Elec/Plmb/HVAC 5/26/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/1/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 6/1/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 6/1/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 6/21/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/21/2022 Not Ready for Inspection DAVID ANDERSON
Shower Pan 6/21/2022 Approved DAVID ANDERSON
Drywall Nailing 6/30/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/30/2022 Approved DAVID ANDERSON
Final 10/31/2022 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 10/31/2022 Approved DAVID ANDERSON
Green Building Final 10/31/2022 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Approved DAVID ANDERSON
Smoke Detectors 10/31/2022 Approved DAVID ANDERSON
Final 11/7/2022 OK to Issue CofO DAVID ANDERSON